1818 N ROSCOMARE ROAD 90077
Certificate Information: 1818 N ROSCOMARE ROAD 90077
- Application / Permit
- 25016-30000-24337
- Plan Check / Job No.
- B25WL06518
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Structural remodel of an (e) SFD. Remodel of the kitchen and family room.
- Permit Issued
- Issued on 12/29/2025
- Issuing Office
- Metro
- Current Status
- Issued on 12/29/2025
Permit Application Status History
| Submitted | 8/11/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/12/2025 | RICHARD GARCIA |
| Corrections Issued | 8/13/2025 | RICHARD GARCIA |
| Building Plans Picked Up | 8/14/2025 | APPLICANT |
| Plan Check Approved | 9/2/2025 | JOHNPAUL ISIP |
| Issued | 12/29/2025 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 9/2/2025 | RICHARD GARCIA |
Contact Information
| Contractor | American Home Improvement Inc; Lic. No.: 835537-B | 20335 VENTURA BLVD #422 WOODLAND HILLS, CA 91364 |
| Engineer | Barajas,, Alejandro Leon; Lic. No.: S4773 | 565 PEARL ST STE 209 LA JOLLA, CA 92037 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/14/2026 | Conditional Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 1/15/2026 | Approved | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 1/23/2026 | Not Ready for Inspection | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 1/23/2026 | Not Ready for Inspection | CHRISTOPHER WILSON |
| HVAC-Rough | 1/23/2026 | Not Ready for Inspection | CHRISTOPHER WILSON |
| PLUMBING-Rough | 1/23/2026 | Not Ready for Inspection | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 1/30/2026 | Approved | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 1/30/2026 | Approved | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 2/4/2026 | Corrections Issued | CHRISTOPHER WILSON |
| Gas Test | 2/4/2026 | Partial Approval | CHRISTOPHER WILSON |
| HVAC-Rough | 2/4/2026 | Approved | CHRISTOPHER WILSON |
| PLUMBING-Rough | 2/4/2026 | Approved | CHRISTOPHER WILSON |
| Deputy Drilled-In Anchors | 2/6/2026 | Conditional Approval | ANDREW NAVE |
| BUILDING-Rough-Frame | 2/9/2026 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2026 | Partial Approval | CARLOS MATAMOROS |
| Insulation | 2/9/2026 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 2/19/2026 | Corrections Issued | CHRISTOPHER WILSON |
| Drywall Nailing | 2/26/2026 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/26/2026 | Approved | CHRISTOPHER WILSON |