6470 W 85TH PL 90045
Certificate Information: 6470 W 85TH PL 90045
- Application / Permit
- 25016-30000-23911
- Plan Check / Job No.
- B25WL06392
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Detached garage conversion to ADU per GC 66323(a)(1)
- Permit Issued
- Issued on 1/13/2026
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 5/27/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/6/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/7/2025 | HOOMAN HAJIZADEH |
| Corrections Issued | 8/11/2025 | HOOMAN HAJIZADEH |
| Building Plans Picked Up | 8/19/2025 | APPLICANT |
| Applicant returned to address corrections | 10/27/2025 | CARLOS MONTES |
| Plan Check Approved | 11/21/2025 | BEHROUZ KHOKHAR |
| Issued | 1/13/2026 | APPLICANT |
| CofO in Progress | 5/20/2026 | MORRIS JACKSON |
| Permit Finaled | 5/27/2026 | RICHARD STEINBACH |
| CofO Issued | 5/27/2026 | RICHARD STEINBACH |
| Permit Finaled | 5/27/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 8/13/2025 | CHRISTINE REUSCH |
| Sewer availability | Cleared | 8/13/2025 | CHRISTINE REUSCH |
| Eng Process Fee Ord 176,300 | Cleared | 8/14/2025 | CHRISTINE REUSCH |
| Specific Plan | Cleared | 11/18/2025 | PEDRO AYALA |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | D G Custom Construction & Electrical Inc; Lic. No.: 1064657-B | 4544 LANDIS AVE BALDWIN PARK, CA 91706 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/2/2026 | Partial Approval | ANTHONY EGSON |
| Wood Frame | 2/2/2026 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 2/11/2026 | Corrections Issued | JESUS PINEDA |
| Green Building Rough | 2/11/2026 | Not Ready for Inspection | JESUS PINEDA |
| ELECTRICAL-Rough | 2/18/2026 | Corrections Issued | TEMISTOCLES CAAL |
| HVAC-Rough | 2/18/2026 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Rough | 2/18/2026 | Approved | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 2/19/2026 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 2/23/2026 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/23/2026 | Approved | ANTHONY EGSON |
| HVAC-Rough | 2/23/2026 | Approved | ANTHONY EGSON |
| Special/Order Compliance | 2/23/2026 | Partial Inspection | BOBBY KEY |
| Interior/Exterior Lathing | 2/25/2026 | Approved | ANTHONY EGSON |
| Insulation | 2/27/2026 | Approved | ANTHONY EGSON |
| Shower Pan | 2/27/2026 | Approved | ANTHONY EGSON |
| Special/Order Compliance | 2/27/2026 | Partial Inspection | BOBBY KEY |
| Drywall Nailing | 3/4/2026 | Approved | ANTHONY EGSON |
| Green Building Rough | 3/4/2026 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 5/13/2026 | Not Ready for Inspection | MORRIS JACKSON |
| Final | 5/13/2026 | Corrections Issued | MORRIS JACKSON |
| Green Building Final | 5/13/2026 | Approved | MORRIS JACKSON |
| SGSOV-Seismic Gas S/O Valve | 5/13/2026 | SGSOV Approved | MORRIS JACKSON |
| Smoke Detectors | 5/13/2026 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 5/19/2026 | Approved | MORRIS JACKSON |
| Final | 5/19/2026 | OK to Issue CofO | MORRIS JACKSON |
| Service/Power Release | 5/19/2026 | Approved | MORRIS JACKSON |