154 S ANITA AVE 90049
Certificate Information: 154 S ANITA AVE 90049
- Application / Permit
- 25016-30000-21448
- Plan Check / Job No.
- B25WL05638
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remove portion of (e) wall between kitchen + family room as well as add a sink and refurbish the laundry room.
- Permit Issued
- Issued on 7/17/2025
- Issuing Office
- West Los Angeles
- Current Status
- Permit Finaled on 1/28/2026
Permit Application Status History
| Submitted | 7/11/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/11/2025 | HOOMAN HAJIZADEH |
| Corrections Issued | 7/11/2025 | HOOMAN HAJIZADEH |
| Plan Check Approved | 7/17/2025 | AMY GUEVARRA |
| Issued | 7/17/2025 | APPLICANT |
| Permit Finaled | 1/28/2026 | HERBERT GIRON |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Cochrane Construction Inc; Lic. No.: 486666-B | 9111 S LA CIENEGA BLVD #110 INGLEWOOD, CA 90301 |
| Engineer | Lobnan,, Essam; Lic. No.: C78053 | PO BOX 64373 LOS ANGELES, CA 90064 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/7/2025 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 8/8/2025 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 8/19/2025 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Rough | 8/19/2025 | Corrections Issued | HERBERT GIRON |
| HVAC-Rough | 8/19/2025 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 8/19/2025 | Corrections Issued | HERBERT GIRON |
| BUILDING-Rough-Frame | 8/21/2025 | Conditional Approval | HERBERT GIRON |
| ELECTRICAL-Rough | 8/21/2025 | Approved | HERBERT GIRON |
| HVAC-Rough | 8/21/2025 | Approved | HERBERT GIRON |
| PLUMBING-Rough | 8/21/2025 | Conditional Approval | HERBERT GIRON |
| Insulation | 8/25/2025 | Approved | HERBERT GIRON |
| Special/Order Compliance | 8/25/2025 | Partial Inspection | JAYLIN GRAVITTE |
| BUILDING-Rough-Frame | 8/27/2025 | Approved | HERBERT GIRON |
| Drywall Nailing | 8/27/2025 | Approved | HERBERT GIRON |
| Final | 12/15/2025 | Corrections Issued | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 12/15/2025 | SGSOV Not Ready | HERBERT GIRON |
| Smoke Detectors | 12/15/2025 | Corrections Issued | HERBERT GIRON |
| Final | 1/28/2026 | Permit Finaled | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 1/28/2026 | SGSOV Approved | HERBERT GIRON |
| Smoke Detectors | 1/28/2026 | Approved | HERBERT GIRON |