528 N GREENCRAIG ROAD 90049
Certificate Information: 528 N GREENCRAIG ROAD 90049
- Application / Permit
- 25016-30000-20916
- Plan Check / Job No.
- B25WL05487
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Interior structural remodel. Remove wall between kitchen and dining room, new patio doors in living and dining rooms, new windows in kitchen.
- Permit Issued
- Issued on 8/7/2025
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 8/7/2025
Permit Application Status History
| Submitted | 7/3/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/3/2025 | RICHARD GARCIA |
| Corrections Issued | 7/4/2025 | RICHARD GARCIA |
| Building Plans Picked Up | 7/8/2025 | APPLICANT |
| Applicant returned to address corrections | 7/16/2025 | HOOMAN HAJIZADEH |
| Applicant returned to address corrections | 7/18/2025 | DAVID CASTILLO |
| Plan Check Approved | 8/7/2025 | CAROLEAN BASMA |
| Plan Check Approved | 8/7/2025 | CAROLEAN BASMA |
| Issued | 8/7/2025 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 7/22/2025 | LANNY MERRICK |
Contact Information
| Contractor | 5 Star Gc Inc; Lic. No.: 1042892-B | 13871 RED HILL AVE TUSTIN, CA 92780 |
| Engineer | Wilson,, Kalen; Lic. No.: C83753 | 25 AMADOR WAY ALISO VIEJO, CA 92656 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/9/2025 | Corrections Issued | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 10/7/2025 | No Access for Inspection | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 10/7/2025 | No Access for Inspection | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 10/8/2025 | Not Ready for Inspection | HERBERT GIRON |
| Wood Frame | 10/8/2025 | Not Ready for Inspection | HERBERT GIRON |
| BUILDING-Rough-Frame | 10/10/2025 | Partial Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 10/10/2025 | Approved | STEPHANIE SWANSON |
| Wood Frame | 12/4/2025 | Not Ready for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 2/2/2026 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 2/3/2026 | Not Ready for Inspection | JUAN VALENZUELA |
| ELECTRICAL-Rough | 2/6/2026 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 2/19/2026 | Corrections Issued | MICHAEL ALLEN |
| Drywall Nailing | 2/19/2026 | Corrections Issued | MICHAEL ALLEN |
| Wood Frame | 2/23/2026 | Not Ready for Inspection | KEVIN SARGSYAN |
| Wood Frame | 3/26/2026 | Not Ready for Inspection | KEVIN SARGSYAN |
| Wood Frame | 3/31/2026 | Approved | KEVIN SARGSYAN |
| Final | 4/7/2026 | No Access for Inspection | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 4/7/2026 | SGSOV Not Ready | KEVIN SARGSYAN |
| Smoke Detectors | 4/7/2026 | No Access for Inspection | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 4/8/2026 | Partial Approval | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 4/9/2026 | Partial Approval | KEVIN SARGSYAN |