2203 S WELLINGTON ROAD 90016
Certificate Information: 2203 S WELLINGTON ROAD 90016
- Application / Permit
- 25016-30000-19633
- Plan Check / Job No.
- B25WL05094
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Structural remodel of an (e) two story S.F.D. Enclose (e) covered porch and add new concrete stairs. Change opening at rear and add a new stair approach. Remodel of (e) kitchen.
- Permit Issued
- Issued on 7/7/2025
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 7/7/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/20/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/24/2025 | RICHARD GARCIA |
| Corrections Issued | 6/28/2025 | RICHARD GARCIA |
| Building Plans Picked Up | 7/1/2025 | APPLICANT |
| Plan Check Approved | 7/3/2025 | ZENA HADDIS |
| Issued | 7/7/2025 | APPLICANT |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Owner-Builder | , |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/4/2025 | Conditional Approval | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/9/2025 | Partial Approval | JUSTIN HAWLEY |
| Rough-Elec/Plmb/HVAC | 9/9/2025 | Corrections Issued | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 9/18/2025 | Approved | JUSTIN HAWLEY |
| Deputy Wood Construction | 9/18/2025 | Conditional Approval | ALEX COLIN |
| Insulation | 9/18/2025 | Approved | JUSTIN HAWLEY |
| MERV13>=Rough | 9/18/2025 | Approved | JUSTIN HAWLEY |
| Rough-Elec/Plmb/HVAC | 9/18/2025 | Approved | JUSTIN HAWLEY |
| Shower Pan | 9/18/2025 | Approved | JUSTIN HAWLEY |
| Underground Mechanical | 9/18/2025 | Corrections Issued | JUSTIN HAWLEY |
| Drywall Nailing | 9/26/2025 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 9/26/2025 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 9/26/2025 | Approved | JUSTIN HAWLEY |
| Underground Mechanical | 9/26/2025 | Approved | JUSTIN HAWLEY |
| Sewer | 1/9/2026 | Approved | JUSTIN HAWLEY |
| Pre-Inspection | 6/15/2026 | Approved | JUSTIN HAWLEY |