16231 W SEPTO ST 91343
Certificate Information: 16231 W SEPTO ST 91343
- Application / Permit
- 25016-30000-19563
- Plan Check / Job No.
- B25WL05092
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- interior and exterior remodel of existing SFD.
- Permit Issued
- Issued on 7/11/2025
- Issuing Office
- West Los Angeles
- Current Status
- Permit Finaled on 4/2/2026
Permit Application Status History
| Submitted | 6/18/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/18/2025 | KAVIAN REFAHI |
| Corrections Issued | 6/19/2025 | KAVIAN REFAHI |
| Building Plans Picked Up | 6/20/2025 | APPLICANT |
| Plan Check Approved | 7/11/2025 | KAVIAN REFAHI |
| Issued | 7/11/2025 | APPLICANT |
| Permit Finaled | 4/2/2026 | CHRISTOPHER ROJAS |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Nextgen Construction Inc The; Lic. No.: 1092708-B | 6506 RANDI AVE WOODLAND HILLS, CA 91303 |
| Engineer | Taroian,, Armen; Lic. No.: C78011 | 411 PALM DR APT 204 GLENDALE, CA 91202 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2025 | Partial Approval | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 9/29/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 9/29/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 10/10/2025 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 10/10/2025 | Partial Approval | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 11/26/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Wood Frame | 12/5/2025 | Corrections Issued | MICHEL ABAJAN |
| Wood Frame | 12/8/2025 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 12/22/2025 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Rough | 12/22/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 12/22/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Rough-Elec/Plmb/HVAC | 12/22/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Shower Pan | 12/22/2025 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 12/30/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 12/30/2025 | Approved | CHRISTOPHER ROJAS |
| Green Building Rough | 12/30/2025 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 12/30/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Insulation | 12/30/2025 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 12/30/2025 | Partial Approval | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 12/30/2025 | Approved | CHRISTOPHER ROJAS |
| Drywall Nailing | 1/9/2026 | Approved | MICHAEL CORTEZ |
| ELECTRICAL-Rough | 3/27/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Final | 3/27/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| HVAC-Final | 3/27/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| PLUMBING-Final | 3/27/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 3/27/2026 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Smoke Detectors | 3/27/2026 | Approved | CHRISTOPHER ROJAS |
| Final | 4/2/2026 | Permit Finaled | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 4/2/2026 | SGSOV Approved | CHRISTOPHER ROJAS |