575 N ALMOLOYA DR 90272
Certificate Information: 575 N ALMOLOYA DR 90272
- Application / Permit
- 25016-30000-19400
- Plan Check / Job No.
- B25WL05031
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- *** 2025 WILDFIRE ELIGIBLE REBUILD PROJECT *** replace exterior & interior walls & 2nd floor framing per calcs.
- Permit Issued
- Issued on 9/12/2025
- Issuing Office
- Current Status
- Permit Finaled on 6/5/2026
Permit Application Status History
| Submitted | 6/20/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/24/2025 | VU NGUYEN |
| Plan Check Approved | 6/26/2025 | VU NGUYEN |
| Building Plans Picked Up | 7/28/2025 | APPLICANT |
| Issued | 9/12/2025 | APPLICANT |
| Permit Finaled | 6/5/2026 | STEPHANIE SWANSON |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Ind Construction Llc; Lic. No.: 937833-B | 16430 VENTURA BLVD STE 208 ENCINO, CA 91436 |
| Engineer | Varela,, Benjamin; Lic. No.: S5714 | 6007 WASHINGTON BLVD CULVER CITY, CA 90232 |
Inspector Information
| STEPHANIE SWANSON, (213) 469-1255 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 9/17/2025 | Partial Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 9/17/2025 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 9/19/2025 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 9/24/2025 | Approved | DANIEL VERA |
| Insulation | 9/24/2025 | Approved | DANIEL VERA |
| Special/Order Compliance | 9/24/2025 | Corrections Issued | DANIEL VERA |
| Deputy Wood Construction | 9/25/2025 | Conditional Approval | STEPHANIE SWANSON |
| Drywall Nailing | 10/1/2025 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 10/1/2025 | Conditional Approval | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 1/22/2026 | SGSOV Not Ready | BOBBY KEY |
| Final | 5/13/2026 | Corrections Issued | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 5/13/2026 | SGSOV Approved | STEPHANIE SWANSON |
| Smoke Detectors | 5/13/2026 | Not Ready for Inspection | STEPHANIE SWANSON |
| Final | 6/5/2026 | Permit Finaled | STEPHANIE SWANSON |
| Smoke Detectors | 6/5/2026 | Approved | STEPHANIE SWANSON |