17417 W COVELLO ST 91406

Certificate Information: 17417 W COVELLO ST 91406

Application / Permit
25016-30000-17588
Plan Check / Job No.
B25WL04483
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (E) unpermitted detached garage to ADU per IB P/BC 2023-150 and per LAMC 12.22 A.33 (b)(1). Design per licensed engineer.
Permit Issued
Issued on 12/18/2025
Issuing Office
West Los Angeles
Current Status
Issued on 12/18/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/30/2025 APPLICANT
Assigned to Plan Check Engineer 5/30/2025 HOOMAN HAJIZADEH
Corrections Issued 5/31/2025 HOOMAN HAJIZADEH
Building Plans Picked Up 6/4/2025 APPLICANT
Applicant returned to address corrections 11/25/2025 CAROLEAN BASMA
Plan Check Approved 12/11/2025 HOOMAN HAJIZADEH
Issued 12/18/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 9/19/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 9/19/2025 BIAINA HARITUNIAN
Sewer availability Cleared 9/19/2025 BIAINA HARITUNIAN
Construction near power lines Cleared 10/17/2025 GEVORK KARAPETYAN
Eng Process Fee Ord 176,300 Cleared 11/4/2025 STEVE MELGAR

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia,, Francisco Diaz; Lic. No.: C88029 19145 MALABAR ST      SANTA CLARITA, CA 91351

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/24/2025 Partial Inspection GAREN HAYRAPETYAN
Footing/Foundation/Slab 12/30/2025 Approved GAREN HAYRAPETYAN
Special/Order Compliance 1/15/2026 Corrections Issued GAREN HAYRAPETYAN
Wood Frame 1/15/2026 Corrections Issued GAREN HAYRAPETYAN
Pre-Inspection 2/3/2026 Partial Inspection RAUL OLAGI
Special/Order Compliance 3/16/2026 Corrections Issued KIRK SANDERS
Green Building Rough 5/11/2026 Partial Inspection MICHEL ABAJAN
Pre-Inspection 5/11/2026 Partial Inspection MICHEL ABAJAN
Wood Frame 5/11/2026 Not Ready for Inspection MICHEL ABAJAN
Pre-Inspection 6/5/2026 Partial Inspection MICHAEL CORTEZ
Special/Order Compliance 6/12/2026 Corrections Issued JOSE AVILA
Special/Order Compliance 6/18/2026 Partial Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 6/23/2026 Approved MICHAEL CORTEZ
Drywall Nailing 6/26/2026 Approved MICHAEL CORTEZ
Green Building Rough 6/26/2026 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 6/26/2026 Approved MICHAEL CORTEZ
Footing/Foundation/Slab 7/1/2026 Approved MICHAEL CORTEZ