4013 N STONE CANYON AVE 91403
Certificate Information: 4013 N STONE CANYON AVE 91403
- Application / Permit
- 25016-30000-16286
- Plan Check / Job No.
- B25WL04060
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (E) garage conversion to storage and ADU per GC 66323(a)(1)
- Permit Issued
- Issued on 7/16/2025
- Issuing Office
- Valley
- Current Status
- Issued on 7/16/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/16/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/19/2025 | KAVIAN REFAHI |
| Corrections Issued | 5/19/2025 | KAVIAN REFAHI |
| Building Plans Picked Up | 5/21/2025 | APPLICANT |
| Applicant returned to address corrections | 6/3/2025 | AMY GUEVARRA |
| Plan Check Approved | 7/14/2025 | JAHANSHAH POURHASSAN |
| Issued | 7/16/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 5/28/2025 | JOHN LIN |
| Eng Process Fee Ord 176,300 | Cleared | 5/28/2025 | JOHN LIN |
| Sewer availability | Cleared | 5/28/2025 | JOHN LIN |
| Grading Pre-Inspection | Cleared | 6/3/2025 | AMY GUEVARRA |
| Construction near power lines | Cleared | 7/10/2025 | GEVORK KARAPETYAN |
Contact Information
| Architect | Andrews,, John Tiger; Lic. No.: C15605 | 2109 STONER AVE LOS ANGELES, CA 90025 |
| Contractor | Juan M Marquez Alvarez De Toledo; Lic. No.: 1059210-B | 2788 GERRY RD CAMARILLO, CA 93012 |
| Engineer | Medina,, Ferdinand Casaclang; Lic. No.: C88007 | 1051 S HOLT AVE APT F LOS ANGELES, CA 90035 |
Inspector Information
| DAVID ANDERSON, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/15/2025 | Corrections Issued | JACK KARGODORIAN |
| PLUMBING-Rough | 8/15/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Underground Mechanical | 8/15/2025 | Corrections Issued | JACK KARGODORIAN |
| Footing/Foundation/Slab | 8/20/2025 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 8/20/2025 | Partial Approval | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 9/10/2025 | Corrections Issued | JACK KARGODORIAN |
| ELECTRICAL-Rough | 9/10/2025 | Approved | JACK KARGODORIAN |
| Green Building Rough | 9/10/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| PLUMBING-Rough | 9/10/2025 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Rough | 10/14/2025 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/14/2025 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 10/14/2025 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 10/14/2025 | Approved | JACK KARGODORIAN |
| Wood Frame | 10/14/2025 | Approved | JACK KARGODORIAN |
| Insulation | 11/5/2025 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 11/12/2025 | Approved | JACK KARGODORIAN |