7658-7660 N LENA AVE 91304

Certificate Information: 7658-7660 N LENA AVE 91304

Application / Permit
25016-30000-15889
Plan Check / Job No.
B25WL03950
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert existing attached garage into an ADU per GC 66323(a)(1). construction per WFPP
Permit Issued
Issued on 5/27/2025
Issuing Office
West Los Angeles
Current Status
CofO Issued on 8/21/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/14/2025 APPLICANT
Assigned to Plan Check Engineer 5/15/2025 RICHARD GARCIA
Corrections Issued 5/17/2025 RICHARD GARCIA
Plan Check Approved 5/27/2025 KAVIAN REFAHI
Issued 5/27/2025 APPLICANT
CofO in Progress 8/19/2025 CHRIS CHRISTENSEN
Permit Finaled 8/21/2025 JOHN JANSON
CofO Issued 8/21/2025 JOHN JANSON
Permit Finaled 8/21/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 5/21/2025 SAFA JAVANMARDI
Sewer availability Cleared 5/21/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 5/22/2025 SAFA JAVANMARDI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/4/2025 Approved CHRIS CHRISTENSEN
Underground Mechanical 6/4/2025 Conditional Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 6/18/2025 Not Ready for Inspection CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 6/18/2025 Partial Approval CHRIS CHRISTENSEN
Green Building Rough 6/18/2025 Not Ready for Inspection CHRIS CHRISTENSEN
Shower Pan 6/18/2025 Not Ready for Inspection CHRIS CHRISTENSEN
Underground Mechanical 6/18/2025 Partial Approval CHRIS CHRISTENSEN
Wood Frame 6/18/2025 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 6/26/2025 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 6/26/2025 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 6/26/2025 Partial Approval CHRIS CHRISTENSEN
Green Building Rough 6/26/2025 Approved CHRIS CHRISTENSEN
HVAC-Rough 6/26/2025 Approved CHRIS CHRISTENSEN
Insulation 6/26/2025 Not Ready for Inspection CHRIS CHRISTENSEN
Interior/Exterior Lathing 6/26/2025 Partial Approval CHRIS CHRISTENSEN
PLUMBING-Rough 6/26/2025 Approved CHRIS CHRISTENSEN
Sewer 6/26/2025 Approved CHRIS CHRISTENSEN
Shower Pan 6/26/2025 Approved CHRIS CHRISTENSEN
Insulation 7/1/2025 Approved TROY SANDERS
Drywall Nailing 7/9/2025 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 8/8/2025 Not Ready for Inspection JEFFREY HARTLINE
Final 8/8/2025 Not Ready for Inspection JEFFREY HARTLINE
Green Building Final 8/8/2025 Not Ready for Inspection JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 8/8/2025 SGSOV Not Ready JEFFREY HARTLINE
Smoke Detectors 8/8/2025 Not Ready for Inspection JEFFREY HARTLINE
BUILDING-Rough-Frame 8/13/2025 Approved JEFFREY HARTLINE
Final 8/13/2025 Not Ready for Inspection JEFFREY HARTLINE
Green Building Final 8/13/2025 Not Ready for Inspection JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 8/13/2025 SGSOV Not Ready JEFFREY HARTLINE
Smoke Detectors 8/13/2025 Not Ready for Inspection JEFFREY HARTLINE
ELECTRICAL-Final 8/18/2025 Approved CHRIS CHRISTENSEN
Final 8/18/2025 OK to Issue CofO CHRIS CHRISTENSEN
Green Building Final 8/18/2025 Approved CHRIS CHRISTENSEN
HVAC-Final 8/18/2025 Approved CHRIS CHRISTENSEN
PLUMBING-Final 8/18/2025 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 8/18/2025 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 8/18/2025 Approved CHRIS CHRISTENSEN