11268 W CASHMERE ST 90049

Certificate Information: 11268 W CASHMERE ST 90049

Application / Permit
25016-30000-13448
Plan Check / Job No.
B25WL03378
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Interior Remodel & Convert attached garage into living space to (E) Single Family Dwelling per engineer's calcs. No replacement parking required per AB 2097
Permit Issued
Issued on 5/12/2025
Issuing Office
West Los Angeles
Current Status
CofO Issued on 11/19/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/28/2025 APPLICANT
Assigned to Plan Check Engineer 4/28/2025 AMY GUEVARRA
Corrections Issued 4/30/2025 AMY GUEVARRA
Building Plans Picked Up 4/30/2025 APPLICANT
Plan Check Approved 5/8/2025 JAHANSHAH POURHASSAN
Issued 5/12/2025 APPLICANT
CofO in Progress 11/17/2025 CARLOS MATAMOROS
Permit Finaled 11/19/2025 RICHARD STEINBACH
CofO Issued 11/19/2025 RICHARD STEINBACH
Permit Finaled 11/19/2025 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/30/2025 LIAM ODONOVAN
Sewer availability Cleared 4/30/2025 LIAM ODONOVAN
Specific Plan Cleared 5/7/2025 RICHARD WOO

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor Dolan Design & Build Llc; Lic. No.: 1135363-B       ,
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/20/2025 Conditional Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 5/22/2025 Approved CARLOS MATAMOROS
Footing/Foundation/Slab 5/22/2025 Approved CARLOS MATAMOROS
HVAC-Rough 7/9/2025 Partial Approval MEL KHACHATOURIAN
PLUMBING-Rough 7/9/2025 Partial Approval MEL KHACHATOURIAN
PLUMBING-Rough 7/11/2025 Not Ready for Inspection DANIEL VERA
ELECTRICAL-Rough 7/18/2025 Corrections Issued DANIEL VERA
Deputy Wood Construction 7/22/2025 Conditional Approval MICHAEL PELHAM
Deputy Reinf. Concrete 7/25/2025 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 7/29/2025 Corrections Issued BOBBY KEY
Interior/Exterior Lathing 8/6/2025 Approved CARLOS MATAMOROS
ELECTRICAL-Rough 8/7/2025 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 8/11/2025 Approved CARLOS MATAMOROS
Gas Test 8/11/2025 Approved CARLOS MATAMOROS
Green Building Rough 8/11/2025 Approved CARLOS MATAMOROS
HVAC-Rough 8/11/2025 Approved CARLOS MATAMOROS
MERV13>=Rough 8/11/2025 Approved CARLOS MATAMOROS
PLUMBING-Rough 8/11/2025 Approved CARLOS MATAMOROS
Insulation 8/13/2025 Approved CARLOS MATAMOROS
Drywall Nailing 8/19/2025 Approved CHRISTOPHER WILSON
Shower Pan 8/19/2025 Not Ready for Inspection CHRISTOPHER WILSON
Interior/Exterior Lathing 8/27/2025 Approved SEAN HAUPT
Shower Pan 8/27/2025 Approved SEAN HAUPT
ELECTRICAL-Final 10/6/2025 Corrections Issued CARLOS MATAMOROS
Service/Power Release 10/6/2025 Not Ready for Inspection CARLOS MATAMOROS
ELECTRICAL-Final 10/15/2025 Not Ready for Inspection CARLOS MATAMOROS
PLUMBING-Final 10/15/2025 Not Ready for Inspection CARLOS MATAMOROS
Gas Test 11/7/2025 Approved CARLOS MATAMOROS
HVAC-Final 11/7/2025 Approved CARLOS MATAMOROS
PLUMBING-Final 11/7/2025 Approved CARLOS MATAMOROS
ELECTRICAL-Final 11/12/2025 Approved CARLOS MATAMOROS
Final 11/12/2025 Corrections Issued CARLOS MATAMOROS
MERV13>=Final 11/12/2025 Approved CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 11/12/2025 SGSOV Approved CARLOS MATAMOROS
Smoke Detectors 11/12/2025 Approved CARLOS MATAMOROS
Final 11/17/2025 OK to Issue CofO CARLOS MATAMOROS