3512-3512 1/2 E ANNETTE ST 90065

Certificate Information: 3512-3512 1/2 E ANNETTE ST 90065

Application / Permit
25016-30000-11384
Plan Check / Job No.
B25WL02963
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Convert existing attached garage into JADU per GC66323(a)(1) and66333 per WFPP
Permit Issued
Issued on 5/27/2025
Issuing Office
West Los Angeles
Current Status
CofO Issued on 9/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/11/2025 APPLICANT
Assigned to Plan Check Engineer 4/11/2025 HOOMAN HAJIZADEH
Corrections Issued 4/11/2025 HOOMAN HAJIZADEH
Applicant returned to address corrections 5/27/2025 JOHNPAUL ISIP
Plan Check Approved 5/27/2025 JOHNPAUL ISIP
Issued 5/27/2025 APPLICANT
CofO in Progress 9/15/2025 BRENDAN MORELLI
Permit Finaled 9/16/2025 DEROLD HAUFF
CofO Issued 9/16/2025 DEROLD HAUFF
Permit Finaled 9/16/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/17/2025 WALLIE JONG
Sewer availability Cleared 4/17/2025 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 4/30/2025 WALLIE JONG
Specific Plan Cleared 5/15/2025 PABLO ESTRADA
Grading Pre-Inspection Cleared 5/19/2025 JOHNPAUL ISIP

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/13/2025 Approved ALIZAH MAYAGOITIA
HVAC-Rough 6/13/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Rough 6/13/2025 Partial Approval ALIZAH MAYAGOITIA
Rough-Elec/Plmb/HVAC 6/13/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Rough-Elec/Plmb/HVAC 7/1/2025 Approved ALIZAH MAYAGOITIA
Wood Frame 7/1/2025 Approved ALIZAH MAYAGOITIA
Insulation 7/8/2025 Corrections Issued REGINA MENDEZ
Interior/Exterior Lathing 7/8/2025 Approved REGINA MENDEZ
Drywall Nailing 7/15/2025 Not Ready for Inspection REGINA MENDEZ
Interior/Exterior Lathing 7/18/2025 Approved GEM DE OCAMPO
Deputy Drilled-In Anchors 7/28/2025 Conditional Approval REGINA MENDEZ
Drywall Nailing 7/29/2025 Approved REGINA MENDEZ
Insulation 7/29/2025 Approved REGINA MENDEZ
BUILDING-Rough-Frame 9/10/2025 Approved ALIZAH MAYAGOITIA
Final 9/10/2025 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 9/10/2025 Approved ALIZAH MAYAGOITIA
Green Building Rough 9/10/2025 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 9/10/2025 SGSOV Approved ALIZAH MAYAGOITIA
Smoke Detectors 9/10/2025 Approved ALIZAH MAYAGOITIA
Final 9/12/2025 OK to Issue CofO BRENDAN MORELLI