7330-7332 W 90TH ST 90045

Certificate Information: 7330-7332 W 90TH ST 90045

Application / Permit
25016-30000-10143
Plan Check / Job No.
B25WL02668
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
conversion of family room & bath to JADU per GC 66323(a)(1) and 66333
Permit Issued
Issued on 5/12/2025
Issuing Office
Valley
Current Status
CofO Issued on 8/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/3/2025 APPLICANT
Assigned to Plan Check Engineer 4/4/2025 KAVIAN REFAHI
Corrections Issued 4/5/2025 KAVIAN REFAHI
Building Plans Picked Up 4/10/2025 APPLICANT
Plan Check Approved 4/25/2025 HOOMAN HAJIZADEH
Issued 5/12/2025 APPLICANT
CofO in Progress 8/8/2025 JESUS PINEDA
Permit Finaled 8/12/2025 RICHARD STEINBACH
CofO Issued 8/12/2025 RICHARD STEINBACH
Permit Finaled 8/12/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 4/16/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 4/16/2025 BIAINA HARITUNIAN
Sewer availability Cleared 4/16/2025 BIAINA HARITUNIAN

Contact Information

Architect Didvar-Saadi,, Sarah; Lic. No.: C25408 4241 TIVOLI AVENUE      LOS ANGELES, CA 90066
Contractor R M Builders & Development Corp; Lic. No.: 995382-B 11958 ART STREET      SUN VALLEY, CA 91352
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/2/2025 Approved BOBBY KEY
ELECTRICAL-Rough 6/24/2025 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 6/24/2025 Approved JESUS RODRIGUEZ
HVAC-Rough 6/24/2025 Approved JESUS RODRIGUEZ
Insulation 6/24/2025 Partial Approval JESUS RODRIGUEZ
PLUMBING-Rough 6/24/2025 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 6/26/2025 Partial Approval JAYLIN GRAVITTE
Shower Pan 6/26/2025 Approved JAYLIN GRAVITTE
BUILDING-Rough-Frame 6/27/2025 Approved JESUS RODRIGUEZ
Gas Test 6/27/2025 Partial Approval JESUS RODRIGUEZ
Drywall Nailing 7/2/2025 Approved JAYLIN GRAVITTE
Insulation 7/2/2025 Approved JAYLIN GRAVITTE
Interior/Exterior Lathing 7/2/2025 Approved JAYLIN GRAVITTE
ELECTRICAL-Final 7/31/2025 Corrections Issued JESUS PINEDA
Final 7/31/2025 Corrections Issued JESUS PINEDA
HVAC-Final 7/31/2025 Corrections Issued JESUS PINEDA
PLUMBING-Final 7/31/2025 Corrections Issued JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 7/31/2025 SGSOV Not Ready JESUS PINEDA
Smoke Detectors 7/31/2025 Approved JESUS PINEDA
ELECTRICAL-Final 8/7/2025 Approved JESUS PINEDA
Final 8/7/2025 OK to Issue CofO JESUS PINEDA
HVAC-Final 8/7/2025 Approved JESUS PINEDA
PLUMBING-Final 8/7/2025 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 8/7/2025 SGSOV Approved JESUS PINEDA