1264 N MONUMENT ST 90272

Certificate Information: 1264 N MONUMENT ST 90272

Application / Permit
25016-30000-08867
Plan Check / Job No.
B25WL02349
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, (2)-STORY. NFPA 13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 6/18/2025
Issuing Office
Valley
Current Status
Issued on 6/18/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/25/2025 APPLICANT
Assigned to Plan Check Engineer 3/26/2025 SERGIO SILVA
Corrections Issued 4/10/2025 SERGIO SILVA
Quality Review Completed 4/10/2025 CHIHARU SUZUKI
Building Plans Picked Up 4/14/2025 APPLICANT
Applicant returned to address corrections 6/2/2025 SERGIO SILVA
Plan Check Approved 6/17/2025 SERGIO SILVA
Issued 6/18/2025 APPLICANT

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 4/18/2025 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 4/18/2025 HISASHI KOBAYAKAWA
Miscellaneous Cleared 4/18/2025 HISASHI KOBAYAKAWA
Permit Cleared 4/18/2025 HISASHI KOBAYAKAWA
Roof/Waste drainage to street Cleared 4/18/2025 HISASHI KOBAYAKAWA
Sewer availability Cleared 4/18/2025 HISASHI KOBAYAKAWA
Hydrant and Access approval Cleared 4/24/2025 PATRICK PEREZ
Low Impact Development (LID) Cleared 5/2/2025 SARAH YOUSSEF
Construction near power lines Cleared 5/14/2025 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Moser,, Bradley Charles; Lic. No.: C68803 116 OAKSIDE LN      BUELLTON, CA 93427

Inspector Information

TEMISTOCLES CAAL, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI
JESUS PINEDA, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/14/2025 Partial Approval BOBBY KEY
Footing/Foundation/Slab 7/14/2025 Corrections Issued BOBBY KEY
Deputy Steel/Welding 8/5/2025 Approved STEPHANIE SWANSON
PLUMBING-Rough 8/5/2025 Partial Approval STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 8/6/2025 Approved STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 8/6/2025 Partial Approval STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 8/7/2025 Partial Approval STEPHANIE SWANSON
Deputy Wood Construction 9/9/2025 Conditional Approval TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 9/25/2025 Conditional Approval TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 10/8/2025 Partial Approval TEMISTOCLES CAAL
HVAC-Rough 12/4/2025 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Rough 12/23/2025 Corrections Issued MICHAEL ALLEN
Gas Test 12/23/2025 Approved MICHAEL ALLEN
Interior/Exterior Lathing 12/23/2025 Not Ready for Inspection MICHAEL ALLEN
PLUMBING-Rough 12/23/2025 Corrections Issued MICHAEL ALLEN
Shower Pan 12/23/2025 Corrections Issued MICHAEL ALLEN
Interior/Exterior Lathing 12/30/2025 Partial Approval MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 1/6/2026 Approved TEMISTOCLES CAAL
Shower Pan 1/6/2026 Approved TEMISTOCLES CAAL
ELECTRICAL-Rough 1/13/2026 Approved TEMISTOCLES CAAL
PLUMBING-Rough 1/13/2026 Corrections Issued TEMISTOCLES CAAL
BUILDING-Rough-Frame 2/5/2026 Conditional Approval TEMISTOCLES CAAL
Green Building Rough 2/5/2026 Approved TEMISTOCLES CAAL
HVAC-Rough 2/5/2026 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 2/5/2026 Partial Approval TEMISTOCLES CAAL
PLUMBING-Rough 2/5/2026 Approved TEMISTOCLES CAAL
Verify Sprinkler Sign Off 2/5/2026 Approved TEMISTOCLES CAAL
Pre-Inspection 2/10/2026 Partial Inspection TEMISTOCLES CAAL
Insulation 2/14/2026 Conditional Approval TEMISTOCLES CAAL
Insulation 2/14/2026 Off-Hour Fees Due
Drywall Nailing 2/20/2026 Conditional Approval TEMISTOCLES CAAL
BUILDING-Rough-Frame 4/7/2026 Approved TEMISTOCLES CAAL
Drywall Nailing 4/7/2026 Approved TEMISTOCLES CAAL
Insulation 4/7/2026 Approved TEMISTOCLES CAAL