842 N LAS CASAS AVE 90272
Certificate Information: 842 N LAS CASAS AVE 90272
- Application / Permit
- 25016-30000-08456
- Plan Check / Job No.
- B25WL02281
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, 3-STORY. NFPA 13D SPRINKLERS THROUGHOUT. EO1
- Permit Issued
- Issued on 9/11/2025
- Issuing Office
- Current Status
- Issued on 9/11/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/22/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/24/2025 | SERGIO SILVA |
| Corrections Issued | 4/2/2025 | SERGIO SILVA |
| Quality Review Completed | 4/3/2025 | CHIHARU SUZUKI |
| Building Plans Picked Up | 4/3/2025 | APPLICANT |
| Applicant returned to address corrections | 4/30/2025 | SERGIO SILVA |
| Applicant returned to address corrections | 6/27/2025 | SERGIO SILVA |
| Plan Check Approved | 9/4/2025 | SERGIO SILVA |
| Issued | 9/11/2025 | APPLICANT |
Permit Application Clearance Information
| Permit | Cleared | 4/7/2025 | JESSICA OPINION |
| Sewer availability | Cleared | 4/7/2025 | JESSICA OPINION |
| BHO/Hillside ordinance | Cleared | 4/8/2025 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 4/8/2025 | HISASHI KOBAYAKAWA |
| Roof/Waste drainage to street | Cleared | 4/8/2025 | HISASHI KOBAYAKAWA |
| Watercourse | Cleared | 4/8/2025 | HISASHI KOBAYAKAWA |
| Distance to fire station | Cleared | 4/9/2025 | PATRICK PEREZ |
| Hydrant and Access approval | Cleared | 4/9/2025 | PATRICK PEREZ |
| Building over 36-ft | Cleared | 9/4/2025 | CALOSHA APPROVED |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Westward Homes; Lic. No.: 1141816-B | 8581 SANTA MONICA BLVD #713 WEST HOLLYWOOD, CA 90069 |
Inspector Information
| DANIEL VERA, (213) 577-9924 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/29/2025 | Partial Inspection | BOBBY KEY |
| Deputy Drilled-In Anchors | 10/31/2025 | Conditional Approval | BOBBY KEY |
| Excavation/Setback/Form/Re-Bar | 11/3/2025 | Approved | BOBBY KEY |
| PLUMBING-Rough | 11/24/2025 | Partial Approval | JESUS PINEDA |
| Excavation/Setback/Form/Re-Bar | 12/3/2025 | Partial Approval | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 12/22/2025 | Partial Approval | STEPHANIE SWANSON |
| Deputy Steel/Welding | 1/6/2026 | Conditional Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/9/2026 | Partial Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/26/2026 | Partial Approval | BOBBY KEY |
| Structural Steel Frame | 2/11/2026 | Approved | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 2/18/2026 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 2/26/2026 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 2/27/2026 | Not Ready for Inspection | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2026 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 3/3/2026 | Approved | BOBBY KEY |
| Underground Mechanical | 3/3/2026 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2026 | Corrections Issued | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 3/27/2026 | Partial Approval | BOBBY KEY |
| HVAC-Rough | 4/13/2026 | Partial Approval | BOBBY KEY |
| BUILDING-Rough-Frame | 4/15/2026 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Rough | 4/15/2026 | Conditional Approval | BOBBY KEY |
| HVAC-Rough | 4/15/2026 | Conditional Approval | BOBBY KEY |
| ELECTRICAL-Rough | 4/20/2026 | Approved | BOBBY KEY |
| HVAC-Rough | 4/20/2026 | Approved | BOBBY KEY |
| Insulation | 4/27/2026 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Rough | 4/27/2026 | Corrections Issued | BOBBY KEY |
| Interior/Exterior Lathing | 4/29/2026 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 5/1/2026 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 5/18/2026 | Corrections Issued | DANIEL VERA |
| FLOOD-Proofing Certificate | 5/18/2026 | Approved | DANIEL VERA |
| Green Building Rough | 5/18/2026 | Approved | DANIEL VERA |
| Verify Sprinkler Sign Off | 5/18/2026 | Approved | DANIEL VERA |
| Insulation | 5/26/2026 | Approved | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2026 | Approved | MICHAEL ALLEN |
| Shower Pan | 6/9/2026 | Approved | DANIEL VERA |
| Drywall Nailing | 6/12/2026 | Approved | DANIEL VERA |
| Interior/Exterior Lathing | 6/23/2026 | Approved | MICHAEL ALLEN |