7704-7706 N INDEPENDENCE AVE 91304

Certificate Information: 7704-7706 N INDEPENDENCE AVE 91304

Application / Permit
25016-30000-08383
Plan Check / Job No.
B25WL02273
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
to convert existing attached garager to ADU per GC 66323(a)(1). construction per WFPP
Permit Issued
Issued on 3/27/2025
Issuing Office
Current Status
CofO Issued on 8/21/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/21/2025 APPLICANT
Assigned to Plan Check Engineer 3/21/2025 KAVIAN REFAHI
Corrections Issued 3/23/2025 KAVIAN REFAHI
Plan Check Approved 3/27/2025 KAVIAN REFAHI
Issued 3/27/2025 APPLICANT
CofO in Progress 5/30/2025 ALEXANDER HANDY
Permit Finaled 8/21/2025 JOHN JANSON
CofO Issued 8/21/2025 JOHN JANSON
Permit Finaled 8/21/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/24/2025 SAFA JAVANMARDI
Sewer availability Cleared 3/24/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 3/25/2025 SAFA JAVANMARDI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/2/2025 Conditional Approval SCOTT SOBEL
PLUMBING-Rough 4/2/2025 Partial Approval SCOTT SOBEL
Deputy Drilled-In Anchors 4/3/2025 Conditional Approval ROBERT GOLD
BUILDING-Rough-Frame 4/10/2025 Not Ready for Inspection JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 4/10/2025 Partial Approval JEFFREY HARTLINE
Green Building Rough 4/10/2025 Not Ready for Inspection JEFFREY HARTLINE
Special/Order Compliance 4/10/2025 Corrections Issued JEFFREY HARTLINE
BUILDING-Rough-Frame 4/18/2025 Conditional Approval ALEXANDER HANDY
ELECTRICAL-Rough 4/18/2025 Approved ALEXANDER HANDY
Green Building Rough 4/18/2025 Approved ALEXANDER HANDY
HVAC-Rough 4/18/2025 Approved ALEXANDER HANDY
Interior/Exterior Lathing 4/18/2025 Corrections Issued ALEXANDER HANDY
PLUMBING-Rough 4/18/2025 Approved ALEXANDER HANDY
Sewer 4/18/2025 Approved ALEXANDER HANDY
Shower Pan 4/18/2025 Approved ALEXANDER HANDY
Pre-Inspection 4/24/2025 Off-Hour Fees Due
Drywall Nailing 4/28/2025 Approved ALEXANDER HANDY
Insulation 4/28/2025 Approved ALEXANDER HANDY
Interior/Exterior Lathing 4/28/2025 Approved ALEXANDER HANDY
BUILDING-Rough-Frame 5/29/2025 Approved ALEXANDER HANDY
ELECTRICAL-Final 5/29/2025 Approved ALEXANDER HANDY
Final 5/29/2025 OK to Issue CofO ALEXANDER HANDY
Green Building Final 5/29/2025 Approved ALEXANDER HANDY
HVAC-Final 5/29/2025 Approved ALEXANDER HANDY
PLUMBING-Final 5/29/2025 Approved ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 5/29/2025 SGSOV Approved ALEXANDER HANDY
Service/Power Release 5/29/2025 Approved ALEXANDER HANDY
Smoke Detectors 5/29/2025 Approved ALEXANDER HANDY