481 S DALEHURST AVE 90024
Certificate Information: 481 S DALEHURST AVE 90024
- Application / Permit
- 25016-30000-07666
- Plan Check / Job No.
- B25WL02130
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (E) 1-story detached garage to ADU per GC 66323(a)(1). All work to be done per WFPP
- Permit Issued
- Issued on 6/23/2025
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 12/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/18/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/18/2025 | DAVID CASTILLO |
| Corrections Issued | 3/25/2025 | DAVID CASTILLO |
| Building Plans Picked Up | 4/1/2025 | APPLICANT |
| Plan Check Approved | 6/16/2025 | ALFREDO JARA |
| Issued | 6/23/2025 | APPLICANT |
| CofO in Progress | 11/25/2025 | DANIEL VERA |
| Permit Finaled | 12/6/2025 | RICHARD STEINBACH |
| CofO Issued | 12/6/2025 | RICHARD STEINBACH |
| Permit Finaled | 12/6/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 4/3/2025 | XOCHITL ARQUIETA |
| Eng Process Fee Ord 176,300 | Cleared | 4/3/2025 | XOCHITL ARQUIETA |
| Roof/Waste drainage to street | Cleared | 4/3/2025 | XOCHITL ARQUIETA |
| Sewer availability | Cleared | 4/3/2025 | XOCHITL ARQUIETA |
| Grading Pre-Inspection | Cleared | 4/7/2025 | LANNY MERRICK |
| Specific Plan | Cleared | 5/29/2025 | JOSHUA JONES |
Contact Information
| Contractor | Twin Set Development Inc; Lic. No.: 796239-B | 5609 YOLANDA AVE #572292 TARZANA, CA 91356 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 8/14/2025 | Conditional Approval | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 8/14/2025 | Approved | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 8/14/2025 | Approved | STEPHANIE SWANSON |
| HVAC-Rough | 8/14/2025 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 8/14/2025 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 8/15/2025 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 8/15/2025 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 8/15/2025 | Approved | CARLOS MATAMOROS |
| Insulation | 8/22/2025 | Approved | DANIEL VERA |
| Shower Pan | 8/27/2025 | Approved | DANIEL VERA |
| Drywall Nailing | 9/2/2025 | Partial Approval | DANIEL VERA |
| Interior/Exterior Lathing | 9/2/2025 | Approved | DANIEL VERA |
| Drywall Nailing | 9/16/2025 | Approved | DANIEL VERA |
| Footing/Foundation/Slab | 10/3/2025 | Approved | DANIEL VERA |
| BUILDING-Rough-Frame | 11/4/2025 | Conditional Approval | DANIEL VERA |
| ELECTRICAL-Final | 11/4/2025 | Approved | DANIEL VERA |
| FLOOD-Proofing Certificate | 11/4/2025 | Not Ready for Inspection | DANIEL VERA |
| Final | 11/4/2025 | Corrections Issued | DANIEL VERA |
| HVAC-Final | 11/4/2025 | Corrections Issued | DANIEL VERA |
| PLUMBING-Final | 11/4/2025 | Approved | DANIEL VERA |
| SGSOV-Seismic Gas S/O Valve | 11/4/2025 | SGSOV Approved | DANIEL VERA |
| Smoke Detectors | 11/4/2025 | Approved | DANIEL VERA |
| BUILDING-Rough-Frame | 11/10/2025 | Not Ready for Inspection | DANIEL VERA |
| FLOOD-Proofing Certificate | 11/10/2025 | Not Ready for Inspection | DANIEL VERA |
| Final | 11/10/2025 | Not Ready for Inspection | DANIEL VERA |
| BUILDING-Rough-Frame | 11/24/2025 | Approved | DANIEL VERA |
| FLOOD-Proofing Certificate | 11/24/2025 | Approved | DANIEL VERA |
| Final | 11/24/2025 | OK to Issue CofO | DANIEL VERA |
| HVAC-Final | 11/24/2025 | Approved | DANIEL VERA |