20850-20852 W MARTHA ST 91367
Certificate Information: 20850-20852 W MARTHA ST 91367
- Application / Permit
- 25016-30000-06870
- Plan Check / Job No.
- B25WL01919
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Conversion of (E) attached garage into an ADU per GC 66323(a)(1)
- Permit Issued
- Issued on 6/6/2025
- Issuing Office
- Current Status
- CofO Issued on 5/14/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/12/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/13/2025 | ALFREDO JARA |
| Corrections Issued | 3/16/2025 | ALFREDO JARA |
| Building Plans Picked Up | 3/20/2025 | APPLICANT |
| Plan Check Approved | 6/6/2025 | HOOMAN HAJIZADEH |
| Issued | 6/6/2025 | APPLICANT |
| CofO in Progress | 5/5/2026 | ALEXANDER HANDY |
| Permit Finaled | 5/14/2026 | JOHN JANSON |
| CofO Issued | 5/14/2026 | JOHN JANSON |
| Permit Finaled | 5/14/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 3/21/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 3/21/2025 | BIAINA HARITUNIAN |
| Grading Pre-Inspection | Cleared | 3/25/2025 | ROBERT PINA |
| Eng Process Fee Ord 176,300 | Cleared | 3/26/2025 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/26/2025 | Partial Inspection | KRISTEN CAUSEY |
| Footing/Foundation/Slab | 9/3/2025 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Deputy Drilled-In Anchors | 9/4/2025 | Conditional Approval | ROBERT GOLD |
| PLUMBING-Rough | 9/12/2025 | Partial Approval | ALEXANDER HANDY |
| Sewer | 9/12/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| Wood Frame | 9/24/2025 | Partial Approval | ALEXANDER HANDY |
| PLUMBING-Rough | 9/30/2025 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 10/8/2025 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Rough | 10/8/2025 | Conditional Approval | ALEXANDER HANDY |
| Gas Test | 10/8/2025 | Partial Approval | ALEXANDER HANDY |
| HVAC-Rough | 10/8/2025 | Conditional Approval | ALEXANDER HANDY |
| Interior/Exterior Lathing | 10/9/2025 | Partial Approval | ALEXANDER HANDY |
| Shower Pan | 10/9/2025 | Approved | ALEXANDER HANDY |
| Insulation | 10/15/2025 | Corrections Issued | ALEXANDER HANDY |
| Interior/Exterior Lathing | 10/15/2025 | Approved | ALEXANDER HANDY |
| Drywall Nailing | 10/23/2025 | Approved | SCOTT SOBEL |
| Insulation | 10/23/2025 | Approved | SCOTT SOBEL |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2025 | Approved | ALEXANDER HANDY |
| Final | 1/27/2026 | Corrections Issued | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 1/27/2026 | SGSOV Not Ready | ALEXANDER HANDY |
| Smoke Detectors | 1/27/2026 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Final | 4/10/2026 | Approved | ALEXANDER HANDY |
| Final | 4/10/2026 | Partial Inspection | ALEXANDER HANDY |
| HVAC-Final | 4/10/2026 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 4/10/2026 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 4/10/2026 | SGSOV Approved | ALEXANDER HANDY |
| Service/Power Release | 4/10/2026 | Approved | ALEXANDER HANDY |
| Final | 5/5/2026 | OK to Issue CofO | ALEXANDER HANDY |