7400 W 89TH ST 90045
Certificate Information: 7400 W 89TH ST 90045
- Application / Permit
- 25016-30000-06705
- Plan Check / Job No.
- B25WL01872
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- renovation of existing finished basement to include the addition of a 1/2 bathroom and wet bar.
- Permit Issued
- Issued on 5/19/2025
- Issuing Office
- West Los Angeles
- Current Status
- Permit Finaled on 10/31/2025
Permit Application Status History
| Submitted | 3/11/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/11/2025 | ZENA HADDIS |
| Corrections Issued | 3/11/2025 | ZENA HADDIS |
| Plan Check Approved | 3/13/2025 | ZENA HADDIS |
| Issued | 5/19/2025 | APPLICANT |
| Permit Finaled | 10/31/2025 | JESUS PINEDA |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Dolphin Ten Development Inc; Lic. No.: 1117748-B | 1032 MAPLE STREET SANTA MONICA, CA 90405 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/17/2025 | Corrections Issued | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 9/10/2025 | Approved | JESUS PINEDA |
| Wood Frame | 9/10/2025 | Approved | JESUS PINEDA |
| Insulation | 9/15/2025 | Approved | JESUS PINEDA |
| Drywall Nailing | 9/18/2025 | Approved | MICHAEL ALLEN |
| Final | 10/28/2025 | Corrections Issued | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 10/28/2025 | SGSOV Approved | JESUS PINEDA |
| Smoke Detectors | 10/28/2025 | Approved | JESUS PINEDA |
| Final | 10/31/2025 | Permit Finaled | JESUS PINEDA |