5732 W BRUSHTON ST 90008

Certificate Information: 5732 W BRUSHTON ST 90008

Application / Permit
25016-30000-04824
Plan Check / Job No.
B25WL01284
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL OF AN EXISTING STUDY AND PRIMARY BEDROOM IN A SFD. RENOVATIONS INCLUDE ADDING A NEW BATHROOM AND WALK IN CLOSET, REPLACING EXISTING WINDOWS, WITH STRUCTURAL REVISION WITH IN (E) FOOTPRINT PER ENGINEERING
Permit Issued
Issued on 6/5/2025
Issuing Office
West Los Angeles
Current Status
Permit Finaled on 10/9/2025

Permit Application Status History

Submitted 2/20/2025 APPLICANT
Assigned to Plan Check Engineer 2/20/2025 YASHAR EMAMI
Corrections Issued 2/26/2025 YASHAR EMAMI
Building Plans Picked Up 2/27/2025 APPLICANT
Applicant returned to address corrections 4/1/2025 JOHNPAUL ISIP
Plan Check Approved 4/8/2025 JOHNPAUL ISIP
Issued 6/5/2025 APPLICANT
Permit Finaled 10/8/2025 LUIS CASTRO

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/21/2025 WALLIE JONG
Sewer availability Cleared 3/21/2025 WALLIE JONG
Grading Pre-Inspection Cleared 3/26/2025 RUSSELL BONVOULOIR

Contact Information

Contractor Reliance Builders Llc; Lic. No.: 1000372-B 11500 W OLYMPIC BLVD STE 506      LOS ANGELES, CA 90064
Engineer Erdelyi,, Peter Tibor; Lic. No.: C26962 2999 OVERLAND AVE STE 103      LOS ANGELES, CA 90064

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 6/24/2025 Partial Approval LUIS CASTRO
Footing/Foundation/Slab 6/24/2025 Approved LUIS CASTRO
BUILDING-Rough-Frame 7/16/2025 Conditional Approval LUIS CASTRO
ELECTRICAL-Rough 7/16/2025 Conditional Approval LUIS CASTRO
HVAC-Rough 7/16/2025 Approved LUIS CASTRO
PLUMBING-Rough 7/16/2025 Approved LUIS CASTRO
ELECTRICAL-Rough 7/22/2025 Approved LUIS CASTRO
Interior/Exterior Lathing 7/22/2025 Partial Approval LUIS CASTRO
BUILDING-Rough-Frame 7/23/2025 Approved LUIS CASTRO
Insulation 7/23/2025 Approved LUIS CASTRO
Drywall Nailing 7/25/2025 Approved LUIS CASTRO
Interior/Exterior Lathing 8/20/2025 Approved RONNIE MEDINA
Shower Pan 8/20/2025 Approved RONNIE MEDINA
ELECTRICAL-Final 10/8/2025 Approved LUIS CASTRO
Final 10/8/2025 Permit Finaled LUIS CASTRO
HVAC-Final 10/8/2025 Approved LUIS CASTRO
PLUMBING-Final 10/8/2025 Approved LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 10/8/2025 SGSOV Approved LUIS CASTRO
Smoke Detectors 10/8/2025 Approved LUIS CASTRO