19849-19851 W GRESHAM ST 91324
Certificate Information: 19849-19851 W GRESHAM ST 91324
- Application / Permit
- 25016-30000-04095
- Plan Check / Job No.
- B25WL01111
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Convert (E) attached garage to an Acessory Dwelling Unit per state code GC 66323(a)(1)
- Permit Issued
- Issued on 3/13/2025
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 10/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/13/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/13/2025 | AMY GUEVARRA |
| Corrections Issued | 2/13/2025 | AMY GUEVARRA |
| Applicant returned to address corrections | 3/6/2025 | HOOMAN HAJIZADEH |
| Plan Check Approved | 3/13/2025 | ZENA HADDIS |
| Issued | 3/13/2025 | APPLICANT |
| CofO in Progress | 9/25/2025 | JEFFREY HARTLINE |
| No Progress | 9/26/2025 | HENRY KIM |
| CofO in Progress | 9/26/2025 | HENRY KIM |
| Permit Finaled | 10/17/2025 | JOHN JANSON |
| CofO Issued | 10/17/2025 | JOHN JANSON |
| Permit Finaled | 10/17/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 2/18/2025 | DARIN LAM |
| Roof/Waste drainage to street | Cleared | 2/18/2025 | DARIN LAM |
| Sewer availability | Cleared | 2/18/2025 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 2/19/2025 | DARIN LAM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khorram,, Majid David; Lic. No.: C42380 | 105 JADE VINE IRVINE, CA 92608 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/22/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Underground Mechanical | 5/22/2025 | Approved | JEFFREY HARTLINE |
| Deputy Drilled-In Anchors | 5/27/2025 | Conditional Approval | CHRIS CHRISTENSEN |
| Excavation/Setback/Form/Re-Bar | 6/2/2025 | Approved | JEFFREY HARTLINE |
| Footing/Foundation/Slab | 6/2/2025 | Approved | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2025 | Partial Approval | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 6/26/2025 | Partial Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 7/9/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| HVAC-Rough | 7/9/2025 | Approved | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 7/14/2025 | Approved | JEFFREY HARTLINE |
| ELECTRICAL-Rough | 7/14/2025 | Approved | JEFFREY HARTLINE |
| Green Building Rough | 7/14/2025 | Approved | JEFFREY HARTLINE |
| PLUMBING-Rough | 7/14/2025 | Approved | JEFFREY HARTLINE |
| Insulation | 7/21/2025 | Corrections Issued | JEFFREY PARD |
| Insulation | 7/23/2025 | Approved | JEFFREY HARTLINE |
| Drywall Nailing | 7/28/2025 | Partial Approval | JEFFREY HARTLINE |
| Drywall Nailing | 8/1/2025 | Approved | JEFFREY HARTLINE |
| Final | 9/11/2025 | Corrections Issued | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 9/11/2025 | SGSOV Approved | JEFFREY HARTLINE |
| Smoke Detectors | 9/11/2025 | Corrections Issued | JEFFREY HARTLINE |
| Final | 9/18/2025 | Partial Approval | JEFFREY HARTLINE |
| Smoke Detectors | 9/18/2025 | Approved | JEFFREY HARTLINE |
| Final | 9/25/2025 | OK to Issue CofO | JEFFREY HARTLINE |
| Special/Order Compliance | 9/26/2025 | Corrections Issued | HENRY KIM |