19849-19851 W GRESHAM ST 91324

Certificate Information: 19849-19851 W GRESHAM ST 91324

Application / Permit
25016-30000-04095
Plan Check / Job No.
B25WL01111
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Convert (E) attached garage to an Acessory Dwelling Unit per state code GC 66323(a)(1)
Permit Issued
Issued on 3/13/2025
Issuing Office
West Los Angeles
Current Status
CofO Issued on 10/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/13/2025 APPLICANT
Assigned to Plan Check Engineer 2/13/2025 AMY GUEVARRA
Corrections Issued 2/13/2025 AMY GUEVARRA
Applicant returned to address corrections 3/6/2025 HOOMAN HAJIZADEH
Plan Check Approved 3/13/2025 ZENA HADDIS
Issued 3/13/2025 APPLICANT
CofO in Progress 9/25/2025 JEFFREY HARTLINE
No Progress 9/26/2025 HENRY KIM
CofO in Progress 9/26/2025 HENRY KIM
Permit Finaled 10/17/2025 JOHN JANSON
CofO Issued 10/17/2025 JOHN JANSON
Permit Finaled 10/17/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 2/18/2025 DARIN LAM
Roof/Waste drainage to street Cleared 2/18/2025 DARIN LAM
Sewer availability Cleared 2/18/2025 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 2/19/2025 DARIN LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Khorram,, Majid David; Lic. No.: C42380 105 JADE VINE      IRVINE, CA 92608

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/22/2025 Not Ready for Inspection JEFFREY HARTLINE
Underground Mechanical 5/22/2025 Approved JEFFREY HARTLINE
Deputy Drilled-In Anchors 5/27/2025 Conditional Approval CHRIS CHRISTENSEN
Excavation/Setback/Form/Re-Bar 6/2/2025 Approved JEFFREY HARTLINE
Footing/Foundation/Slab 6/2/2025 Approved JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 6/12/2025 Partial Approval JEFFREY HARTLINE
Interior/Exterior Lathing 6/26/2025 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 7/9/2025 Not Ready for Inspection JEFFREY HARTLINE
HVAC-Rough 7/9/2025 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 7/14/2025 Approved JEFFREY HARTLINE
ELECTRICAL-Rough 7/14/2025 Approved JEFFREY HARTLINE
Green Building Rough 7/14/2025 Approved JEFFREY HARTLINE
PLUMBING-Rough 7/14/2025 Approved JEFFREY HARTLINE
Insulation 7/21/2025 Corrections Issued JEFFREY PARD
Insulation 7/23/2025 Approved JEFFREY HARTLINE
Drywall Nailing 7/28/2025 Partial Approval JEFFREY HARTLINE
Drywall Nailing 8/1/2025 Approved JEFFREY HARTLINE
Final 9/11/2025 Corrections Issued JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 9/11/2025 SGSOV Approved JEFFREY HARTLINE
Smoke Detectors 9/11/2025 Corrections Issued JEFFREY HARTLINE
Final 9/18/2025 Partial Approval JEFFREY HARTLINE
Smoke Detectors 9/18/2025 Approved JEFFREY HARTLINE
Final 9/25/2025 OK to Issue CofO JEFFREY HARTLINE
Special/Order Compliance 9/26/2025 Corrections Issued HENRY KIM