12213 W LAWLER ST 90066

Certificate Information: 12213 W LAWLER ST 90066

Application / Permit
25016-30000-02822
Plan Check / Job No.
B25WL00694
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Remove & replace portion of roof from hip to gable roof, vault the ceiling, 5 new skylights per engineering
Permit Issued
Issued on 3/7/2025
Issuing Office
Valley
Current Status
Permit Finaled on 5/22/2025

Permit Application Status History

Submitted 1/31/2025 APPLICANT
Assigned to Plan Check Engineer 1/31/2025 HOOMAN HAJIZADEH
Corrections Issued 2/4/2025 HOOMAN HAJIZADEH
Building Plans Picked Up 2/5/2025 APPLICANT
Applicant returned to address corrections 2/18/2025 LAWRENCE QUIRANTE
Plan Check Approved 2/19/2025 SERGIO SILVA
Issued 3/7/2025 APPLICANT
Permit Finaled 5/21/2025 WILBER ROSALES

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/13/2025 JUSTIN BICOL
Roof/Waste drainage to street Cleared 2/13/2025 JUSTIN BICOL
Grading Pre-Inspection Cleared 2/19/2025 VASIL MIHALEV

Contact Information

Contractor Principle Building Group Inc; Lic. No.: 984586-B 20936 DEVONSHIRE ST #A-2      CHATSWORTH, CA 91311
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/20/2025 Conditional Approval WILBER ROSALES
Footing/Foundation/Slab 3/21/2025 Approved WILBER ROSALES
Special/Order Compliance 3/21/2025 Partial Inspection TEMISTOCLES CAAL
Special/Order Compliance 3/25/2025 Partial Inspection TEMISTOCLES CAAL
Wood Frame 3/25/2025 Partial Approval WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 4/3/2025 Approved WILBER ROSALES
BUILDING-Rough-Frame 4/11/2025 Partial Approval WILBER ROSALES
Interior/Exterior Lathing 4/11/2025 Approved WILBER ROSALES
Insulation 4/22/2025 Approved WILBER ROSALES
Drywall Nailing 4/24/2025 Approved WILBER ROSALES
Final 5/21/2025 Permit Finaled WILBER ROSALES
SGSOV-Seismic Gas S/O Valve 5/21/2025 SGSOV Approved WILBER ROSALES
Smoke Detectors 5/21/2025 Approved WILBER ROSALES