567 E RIALTO AVE 90291

Certificate Information: 567 E RIALTO AVE 90291

Application / Permit
25016-30000-01454
Plan Check / Job No.
B24WL00937
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Carport
Work Description
Alteration to (E) SFD with attached carport to remove the existing house. leaving only the detached carport
Permit Issued
Issued on 2/18/2025
Issuing Office
West Los Angeles
Current Status
Issued on 2/18/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/3/2024 APPLICANT
Assigned to Plan Check Engineer 5/8/2024 HOOMAN HAJIZADEH
Corrections Issued 5/24/2024 HOOMAN HAJIZADEH
Quality Review Completed 5/30/2024 KAVIAN REFAHI
Building Plans Picked Up 5/31/2024 APPLICANT
Applicant returned to address corrections 10/18/2024 HOOMAN HAJIZADEH
Applicant returned to address corrections 10/23/2024 HOOMAN HAJIZADEH
Applicant returned to address corrections 11/8/2024 HOOMAN HAJIZADEH
Plan Check Approved 2/14/2025 HOOMAN HAJIZADEH
Issued 2/18/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/23/2025 DARIN LAM
Roof/Waste drainage to street Cleared 1/23/2025 DARIN LAM
Coastal Zone Cleared 1/24/2025 DAVID URITA
Historic monument Cleared 1/24/2025 DAVID URITA
Miscellaneous Cleared 1/24/2025 DAVID URITA
Miscellaneous Cleared 1/24/2025 DAVID URITA
Specific Plan Cleared 1/24/2025 DAVID URITA
ZA Case Cleared 1/24/2025 DAVID URITA
ZA Case Cleared 1/24/2025 DAVID URITA
ZA Case Cleared 1/24/2025 DAVID URITA
ZA Case Cleared 1/24/2025 DAVID URITA
ZI Cleared 1/24/2025 DAVID URITA
Flood clearance Cleared 1/28/2025 TUYEN LE
Specific Plan Cleared 1/28/2025 PEDRO AYALA
Specific Plan Cleared 1/28/2025 PEDRO AYALA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/18/2025 Corrections Issued JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 2/13/2026 Corrections Issued RUBEN RIVAS
Excavation/Setback/Form/Re-Bar 3/11/2026 Corrections Issued RUBEN RIVAS
Footing/Foundation/Slab 4/24/2026 Partial Approval RUBEN RIVAS
Footing/Foundation/Slab 5/14/2026 Partial Approval RUBEN RIVAS
Deputy Reinf. Concrete 5/19/2026 Conditional Approval DAVID FEILER