2450 N SILVER LAKE BLVD 90039
Certificate Information: 2450 N SILVER LAKE BLVD 90039
- Application / Permit
- 25016-30000-01150
- Plan Check / Job No.
- B25WL00210
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Fire damage repair to basement area of (e) SFD with att. garage ; replace portion of 1st floor framing
- Permit Issued
- Issued on 1/24/2025
- Issuing Office
- West Los Angeles
- Current Status
- Permit Finaled on 4/24/2026
Permit Application Status History
| Submitted | 1/15/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/15/2025 | REZA HAGHIGHAT |
| Corrections Issued | 1/16/2025 | REZA HAGHIGHAT |
| Building Plans Picked Up | 1/17/2025 | APPLICANT |
| Plan Check Approved | 1/24/2025 | JOHNPAUL ISIP |
| Issued | 1/24/2025 | APPLICANT |
| Permit Finaled | 4/24/2026 | ALIZAH MAYAGOITIA |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Modern Design Cabinet Restorations; Lic. No.: 1066238-C-6 | 27051 RIO PRADO DRIVE VALENCIA, CA 91354 |
| Engineer | Kim,, Eui S; Lic. No.: S5138 | 33204 LAREDO CIR THOUSAND PALMS, CA 92276 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/11/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 2/26/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 2/26/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Wood Frame | 2/26/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 3/6/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 3/6/2025 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 5/8/2025 | Approved | HAMIK HARTOUNIAN |
| Wood Frame | 5/8/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 5/21/2025 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 5/21/2025 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 5/21/2025 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 5/21/2025 | Approved | HAMIK HARTOUNIAN |
| Wood Frame | 5/21/2025 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 5/29/2025 | Approved | REGINA MENDEZ |
| Shower Pan | 7/8/2025 | Approved | ALEX COLIN |
| Final | 4/17/2026 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 4/17/2026 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 4/17/2026 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Smoke Detectors | 4/17/2026 | Approved | HAMIK HARTOUNIAN |
| Final | 4/24/2026 | Permit Finaled | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 4/24/2026 | SGSOV Approved | ALIZAH MAYAGOITIA |