10265 W MONTE MAR DR 90064
Certificate Information: 10265 W MONTE MAR DR 90064
- Application / Permit
- 25016-30000-00868
- Plan Check / Job No.
- B25WL00143
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Structural remodel of (E) SFD. Remodel of the kitchen. Open up the exterior wall w/(n) moment frame in the kitchen and replace (e) exterior doors with (n) exterior doors in the family room.
- Permit Issued
- Issued on 3/19/2025
- Issuing Office
- West Los Angeles
- Current Status
- Permit Finaled on 10/23/2025
Permit Application Status History
| Submitted | 1/13/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/14/2025 | RICHARD GARCIA |
| Corrections Issued | 1/17/2025 | RICHARD GARCIA |
| Building Plans Picked Up | 1/22/2025 | APPLICANT |
| Plan Check Approved | 3/19/2025 | JOHNPAUL ISIP |
| Issued | 3/19/2025 | APPLICANT |
| Permit Finaled | 10/22/2025 | ASHLEY THOMPSON |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | L D L General Contractors Inc; Lic. No.: 856503-B | 7216 LITTLER COURT MOORPARK, CA 93021 |
| Engineer | Vlachos,, Manuel Vassilios; Lic. No.: C64976 | 6832 RIDGEMARK DR MOORPARK, CA 93021 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/20/2025 | Corrections Issued | DANIEL VERA |
| BUILDING-Rough-Frame | 6/10/2025 | Partial Approval | ASHLEY THOMPSON |
| Deputy Reinf. Concrete | 6/12/2025 | Conditional Approval | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 6/18/2025 | Approved | ASHLEY THOMPSON |
| Insulation | 6/18/2025 | Approved | ASHLEY THOMPSON |
| Drywall Nailing | 6/23/2025 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 6/23/2025 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Final | 10/14/2025 | Approved | ASHLEY THOMPSON |
| PLUMBING-Rough | 10/14/2025 | Approved | ASHLEY THOMPSON |
| Final | 10/16/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| PLUMBING-Final | 10/16/2025 | Corrections Issued | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 10/16/2025 | SGSOV Approved | ASHLEY THOMPSON |
| Smoke Detectors | 10/16/2025 | Corrections Issued | ASHLEY THOMPSON |
| Final | 10/21/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| PLUMBING-Final | 10/21/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Smoke Detectors | 10/21/2025 | Approved | ASHLEY THOMPSON |
| Final | 10/22/2025 | Permit Finaled | ASHLEY THOMPSON |
| PLUMBING-Final | 10/22/2025 | Approved | ASHLEY THOMPSON |