1315 N BIENVENEDA AVE 90272
Certificate Information: 1315 N BIENVENEDA AVE 90272
- Application / Permit
- 25016-20001-28192
- Plan Check / Job No.
- B25VN35090
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ****2025 WILDFIRE EO-1 ELIGIBLE REBUILD**** SUPPLEMENTAL TO 25016-30000-28192 FOR 1ST AND 2ND FLOOR ADDITION OVER GARAGE, REMOVE OPEN TRELLIS , ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 1/6/2026
- Issuing Office
- Current Status
- Issued on 1/6/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/4/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 12/4/2025 | RARES BODEA |
| Corrections Issued | 12/9/2025 | RARES BODEA |
| Quality Review Completed | 12/10/2025 | STEVEN KIM |
| Building Plans Picked Up | 12/10/2025 | APPLICANT |
| Applicant returned to address corrections | 12/18/2025 | RARES BODEA |
| Plan Check Approved | 1/6/2026 | RARES BODEA |
| Issued | 1/6/2026 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/8/2025 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 12/8/2025 | CELINA MORENO |
| Sewer availability | Cleared | 12/8/2025 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 12/30/2025 | RUEL COLE |
Contact Information
| Architect | Mcgarry,, James Michael; Lic. No.: C34601 | SANTA MONICA, CA 90405 |
| Contractor | Mano A Mano Llc; Lic. No.: 1107114-B | 5068 W WASHINGTON BLVD LOS ANGELES, CA 90016 |
Inspector Information
| DANIEL VERA, (213) 577-9924 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/7/2026 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 1/9/2026 | Corrections Issued | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 1/9/2026 | Corrections Issued | STEPHANIE SWANSON |
| Structural Steel Frame | 1/9/2026 | Partial Approval | STEPHANIE SWANSON |
| Deputy Wood Construction | 1/13/2026 | Conditional Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 1/20/2026 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 1/20/2026 | Approved | BOBBY KEY |
| Underground Mechanical | 1/20/2026 | Approved | BOBBY KEY |
| Deputy Wood Construction | 2/17/2026 | Conditional Approval | JUAN VALENZUELA |
| ELECTRICAL-Rough | 3/2/2026 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/2/2026 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 3/2/2026 | Not Ready for Inspection | BOBBY KEY |