8363 W 3RD ST 90048
Certificate Information: 8363 W 3RD ST 90048
- Application / Permit
- 25016-20000-38010
- Plan Check / Job No.
- B25VN37913
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant - Take Out
- Work Description
- CHANGE OF USE FROM RETAIL TO RESTAURANT-TAKE OUT
- Permit Issued
- Issued on 4/3/2026
- Issuing Office
- Valley
- Current Status
- Issued on 4/3/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/31/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/9/2026 | JEROME MAGAT PALMA |
| Corrections Issued | 1/10/2026 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 1/13/2026 | APPLICANT |
| Applicant returned to address corrections | 3/25/2026 | SERGIO MUNIZ |
| Plan Check Approved | 4/3/2026 | MINA HABILI |
| Issued | 4/3/2026 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/26/2026 | MICHAEL BROWN |
| Sewer availability | Cleared | 1/26/2026 | MICHAEL BROWN |
| Comm Cor/Mini-Mall | Cleared | 2/24/2026 | ROSALINDA MEZA |
| Food establishment approval | Cleared | 3/25/2026 | LACDHS APPROVED |
| Food Service Establishment | Cleared | 4/2/2026 | ANSON PUA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Braun,, Jason; Lic. No.: C70948 | 14390 SHAWNEE ST MOORPARK, CA 93021 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/16/2026 | Partial Approval | IAN BLINN |
| METHANE-Rough | 5/1/2026 | Not Ready for Inspection | IAN BLINN |
| Wood Frame | 5/1/2026 | Not Ready for Inspection | IAN BLINN |
| METHANE-Rough | 5/7/2026 | Not Ready for Inspection | IAN BLINN |
| Wood Frame | 5/7/2026 | Not Ready for Inspection | IAN BLINN |
| Pre-Inspection | 5/11/2026 | Not Ready for Inspection | IAN BLINN |
| METHANE-Rough | 5/27/2026 | Partial Approval | IAN BLINN |
| Wood Frame | 5/27/2026 | Partial Approval | IAN BLINN |
| Insulation | 5/29/2026 | Partial Approval | IAN BLINN |
| Drywall Nailing | 6/4/2026 | Partial Approval | IAN BLINN |