18215 W SHERMAN WAY 91335
Certificate Information: 18215 W SHERMAN WAY 91335
- Application / Permit
- 25016-20000-37867
- Plan Check / Job No.
- B25VN37775
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- EPLAN: TENANT IMPROVEMENT TO (E) RETAIL STORE FOR EXTERIOR AND INTERIOR REMODEL - NO CHANGE IN PARKING AND USE
- Permit Issued
- Issued on 4/1/2026
- Issuing Office
- Current Status
- Issued on 4/1/2026
Permit Application Status History
| Submitted | 12/30/2025 | APPLICANT |
| Assigned to Zoning Architect | 1/2/2026 | TRIAKSHA KALRA |
| Assigned to Plan Check Engineer | 1/8/2026 | ALFRED RAMIREZ |
| Corrections Issued | 1/11/2026 | ALFRED RAMIREZ |
| Quality Review Completed | 1/14/2026 | STEVEN KIM |
| Applicant returned to address corrections | 3/16/2026 | ALFRED RAMIREZ |
| Plan Check Approved | 3/31/2026 | ALFRED RAMIREZ |
| Issued | 4/1/2026 | APPLICANT |
Permit Application Clearance Information
| "Q" conditions | Cleared | 1/22/2026 | JASON CHAN |
| "Q" conditions | Cleared | 1/22/2026 | JASON CHAN |
| "Q" conditions | Cleared | 1/22/2026 | JASON CHAN |
| CPC | Cleared | 1/22/2026 | JASON CHAN |
| Miscellaneous | Cleared | 1/22/2026 | JASON CHAN |
| Miscellaneous | Cleared | 1/22/2026 | JASON CHAN |
| ZI | Cleared | 3/25/2026 | LAURA FRAZIN-STEELE |
| Zoning Plan Check | Cleared | 3/26/2026 | Sarkis Harabedian |
| DAS Clearance | Cleared | 3/31/2026 | Sarkis Harabedian |
Contact Information
| Contractor | Efraim & Associates Inc; Lic. No.: 757907-B | , |
| Engineer | Young,, Bradley Rae; Lic. No.: S4727 | 345 POLLASKY AVENUE CLOVIS, CA 93612 |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/4/2026 | Partial Approval | ROBERT DAVIS |
| Footing/Foundation/Slab | 5/4/2026 | Partial Approval | ROBERT DAVIS |
| Light Gage Steel Frame | 5/8/2026 | Partial Approval | ROBERT DAVIS |
| Drywall Nailing | 5/15/2026 | Partial Approval | BRIAN KELLY |
| Special/Order Compliance | 6/22/2026 | Partial Inspection | BRIAN KELLY |