7795-7797 N CLEARFIELD AVE 91402
Certificate Information: 7795-7797 N CLEARFIELD AVE 91402
- Application / Permit
- 25016-20000-37849
- Plan Check / Job No.
- B25VN37767
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL (E) SFD, 16'-4" X 10'-1" ADDITION AND CONVERT (E) ATTACHED GARAGE TO JUNIOR ACCESSORY DWELLING UNIT PER GC66323(a)(1) and 66333 ALL WORK PER WFPP
- Permit Issued
- Issued on 1/14/2026
- Issuing Office
- Current Status
- Issued on 1/14/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/29/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/3/2026 | ARTIN ZARUKIAN |
| Corrections Issued | 1/3/2026 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 1/5/2026 | APPLICANT |
| Applicant returned to address corrections | 1/12/2026 | SEWADA ZADOORIAN MILAGARDI |
| Issued | 1/14/2026 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 1/5/2026 | JEREMY CHOK |
| Eng Process Fee Ord 176,300 | Cleared | 1/7/2026 | JEREMY CHOK |
| Sewer availability | Cleared | 1/7/2026 | JEREMY CHOK |
| Address approval | Cleared | 1/12/2026 | MICHAEL BROWN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Insulation | 7/28/2026 |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/20/2026 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 2/20/2026 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 2/20/2026 | Partial Approval | VINCENT HANLEY |
| Sewer | 2/20/2026 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/27/2026 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 6/18/2026 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 6/18/2026 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 6/18/2026 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 7/15/2026 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 7/15/2026 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 7/21/2026 | Approved | OGANES TARAKHCHYAN |