15826 W SEPTO ST 91343
Certificate Information: 15826 W SEPTO ST 91343
- Application / Permit
- 25016-20000-37537
- Plan Check / Job No.
- B25VN37435
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED INT/EXT REMODEL PER PLAN.
- Permit Issued
- Issued on 2/10/2026
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 6/11/2026
Permit Application Status History
| Submitted | 12/23/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 12/23/2025 | HAYATO TSUCHIYA |
| Plans on Hold | 12/31/2025 | ARTIN ZARUKIAN |
| Hold Released | 1/16/2026 | JEROME MAGAT PALMA |
| Corrections Issued | 1/17/2026 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 1/21/2026 | APPLICANT |
| Plan Check Approved | 2/10/2026 | HAYATO TSUCHIYA |
| Issued | 2/10/2026 | APPLICANT |
| Permit Finaled | 6/11/2026 | CHRISTOPHER ROJAS |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 1/23/2026 | MICHAEL TEMPLE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Carrillo,, Jesus Eduardo; Lic. No.: C77737 | 8207 BROOKGREEN RD DOWNEY, CA 90240 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/2/2026 | Approved | KEVIN BERBERYAN |
| HVAC-Rough | 3/18/2026 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 4/14/2026 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 4/14/2026 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 4/21/2026 | Partial Approval | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 4/21/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 4/21/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Wood Frame | 4/21/2026 | Partial Approval | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 4/24/2026 | Approved | NICHOLAS TROWBRIDGE |
| Insulation | 4/24/2026 | Approved | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 4/24/2026 | Partial Approval | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 4/24/2026 | Approved | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 5/1/2026 | Approved | RAUL OLAGI |
| Shower Pan | 5/1/2026 | Approved | RAUL OLAGI |
| Special/Order Compliance | 5/1/2026 | Corrections Issued | RAUL OLAGI |
| Final | 6/5/2026 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 6/5/2026 | SGSOV Approved | CHRISTOPHER ROJAS |
| Smoke Detectors | 6/5/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Final | 6/11/2026 | Permit Finaled | CHRISTOPHER ROJAS |
| Smoke Detectors | 6/11/2026 | Approved | CHRISTOPHER ROJAS |