10415-10417 N GOTHIC AVE 91344

Certificate Information: 10415-10417 N GOTHIC AVE 91344

Application / Permit
25016-20000-36978
Plan Check / Job No.
B25VN36776
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: CONVERT (E) ATTACHED 2-CAR GARAGE TO ACCESSORY DWELLING UNIT PER GCS66323(A)(1). ALL WORK DONE PER ENGINEERING.
Permit Issued
Issued on 1/21/2026
Issuing Office
Current Status
CofO Issued on 6/11/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/17/2025 APPLICANT
Assigned to Plan Check Engineer 12/24/2025 GURUNATH NESARAJAH
Corrections Issued 12/24/2025 GURUNATH NESARAJAH
Plan Check Approved 1/20/2026 GURUNATH NESARAJAH
Issued 1/21/2026 APPLICANT
CofO in Progress 5/20/2026 CHRISTOPHER ROJAS
Permit Finaled 6/11/2026 RUBEN SALAS
CofO Issued 6/11/2026 RUBEN SALAS
Permit Finaled 6/11/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/9/2026 JEFF LOREDO
Sewer availability Cleared 1/9/2026 JEFF LOREDO
Eng Process Fee Ord 176,300 Cleared 1/12/2026 JEFF LOREDO

Contact Information

Contractor Owner-Builder       ,
Engineer Baraty,, Patrick; Lic. No.: S5900 450 NORTH BRAND BLVD STE 600      GLENDALE, CA 91203

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Wood Construction 2/2/2026 Conditional Approval JOSE AVILA
Footing/Foundation/Slab 2/3/2026 Approved CHRISTOPHER ROJAS
Underground Mechanical 2/3/2026 Partial Approval CHRISTOPHER ROJAS
BUILDING-Rough-Frame 2/13/2026 Partial Approval CHRISTOPHER ROJAS
ELECTRICAL-Rough 2/13/2026 Corrections Issued CHRISTOPHER ROJAS
Green Building Rough 2/13/2026 Not Ready for Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 2/18/2026 Approved CHRISTOPHER ROJAS
ELECTRICAL-Rough 2/18/2026 Approved CHRISTOPHER ROJAS
Green Building Rough 2/18/2026 Approved CHRISTOPHER ROJAS
Insulation 2/20/2026 Approved CHRISTOPHER ROJAS
Drywall Nailing 2/25/2026 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 2/25/2026 Partial Approval MICHAEL CORTEZ
Shower Pan 3/11/2026 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 3/16/2026 Approved KEVIN BERBERYAN
ELECTRICAL-Final 4/8/2026 Corrections Issued CHRISTOPHER ROJAS
Final 4/8/2026 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 4/8/2026 Corrections Issued CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 4/8/2026 SGSOV Approved CHRISTOPHER ROJAS
Smoke Detectors 4/8/2026 Approved CHRISTOPHER ROJAS
Final 4/20/2026 Corrections Issued JENNIFER RABUCHIN
Green Building Final 4/20/2026 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 4/20/2026 Corrections Issued JENNIFER RABUCHIN
Final 5/7/2026 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 5/7/2026 Approved CHRISTOPHER ROJAS
Final 5/20/2026 OK to Issue CofO CHRISTOPHER ROJAS