6531-6533 N NEDDY AVE 91307
Certificate Information: 6531-6533 N NEDDY AVE 91307
- Application / Permit
- 25016-20000-36311
- Plan Check / Job No.
- B25VN36079
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: CONVERT (E) ATTACHED GARAGE TO A JADU PER GCS 66323(a)(1) and66333ALL WORK PER ENG.
- Permit Issued
- Issued on 2/5/2026
- Issuing Office
- Current Status
- CofO in Progress on 6/3/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/11/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 12/15/2025 | LUISANGEL VALENZUELA |
| Corrections Issued | 12/16/2025 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 1/14/2026 | SARKIS HARABEDIAN |
| Applicant returned to address corrections | 1/21/2026 | SARKIS HARABEDIAN |
| Plan Check Approved | 2/5/2026 | SARKIS HARABEDIAN |
| Issued | 2/5/2026 | APPLICANT |
| CofO in Progress | 6/3/2026 | TROY SANDERS |
Permit Application Clearance Information
| Address approval | Cleared | 1/5/2026 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 1/5/2026 | JEANIE LAM |
| Sewer availability | Cleared | 1/5/2026 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Jalalpour,, Mohammad; Lic. No.: S6696 | 2610 VISTA DEL ORO NEWPORT BEACH, CA 92660 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/9/2026 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 2/9/2026 | Partial Approval | TROY SANDERS |
| PLUMBING-Rough | 2/9/2026 | Partial Approval | TROY SANDERS |
| PLUMBING-Rough | 2/11/2026 | Partial Approval | TROY SANDERS |
| Sewer | 2/11/2026 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 2/23/2026 | Not Ready for Inspection | GEVORK IPCHYAN |
| Green Building Rough | 2/23/2026 | Not Ready for Inspection | GEVORK IPCHYAN |
| PLUMBING-Rough | 2/23/2026 | Not Ready for Inspection | GEVORK IPCHYAN |
| Sewer | 2/23/2026 | Not Ready for Inspection | GEVORK IPCHYAN |
| Shower Pan | 2/23/2026 | Not Ready for Inspection | GEVORK IPCHYAN |
| Gas Test | 2/26/2026 | Not Ready for Inspection | DAVID FASTIGGI |
| Sewer | 2/26/2026 | Corrections Issued | DAVID FASTIGGI |
| Shower Pan | 2/26/2026 | Corrections Issued | DAVID FASTIGGI |
| BUILDING-Rough-Frame | 3/4/2026 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 3/4/2026 | Approved | TROY SANDERS |
| Green Building Rough | 3/4/2026 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 3/4/2026 | Approved | TROY SANDERS |
| PLUMBING-Rough | 3/4/2026 | Approved | TROY SANDERS |
| Insulation | 3/18/2026 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 3/18/2026 | Approved | TROY SANDERS |
| HVAC-Rough | 3/19/2026 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 4/7/2026 | Approved | TROY SANDERS |
| ELECTRICAL-Final | 5/22/2026 | Approved | TROY SANDERS |
| Final | 5/22/2026 | Not Ready for Inspection | TROY SANDERS |
| Green Building Final | 5/22/2026 | Not Ready for Inspection | TROY SANDERS |
| HVAC-Final | 5/22/2026 | Approved | TROY SANDERS |
| PLUMBING-Final | 5/22/2026 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 5/22/2026 | SGSOV Approved | TROY SANDERS |
| Service/Power Release | 5/22/2026 | Approved | TROY SANDERS |
| Smoke Detectors | 5/22/2026 | Approved | TROY SANDERS |
| Final | 6/2/2026 | OK to Issue CofO | TROY SANDERS |
| Green Building Final | 6/2/2026 | Approved | TROY SANDERS |