6243-6243 1/2 N FALLBROOK AVE 91367

Certificate Information: 6243-6243 1/2 N FALLBROOK AVE 91367

Application / Permit
25016-20000-36302
Plan Check / Job No.
B25VN36055
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN Convert an existing garage to an ADU per GCS 66323 (a)(1) with an interior remodel to existing SFD
Permit Issued
Issued on 2/7/2026
Issuing Office
Current Status
Issued on 2/7/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/11/2025 APPLICANT
Assigned to Plan Check Engineer 12/15/2025 BEHROUZ KHOKHAR
Corrections Issued 12/16/2025 BEHROUZ KHOKHAR
Applicant returned to address corrections 1/13/2026 BEHROUZ KHOKHAR
Applicant returned to address corrections 1/21/2026 DAVID CASTILLO
Applicant returned to address corrections 1/26/2026 DAVID CASTILLO
Plan Check Approved 1/30/2026 DAVID CASTILLO
Issued 2/7/2026 APPLICANT

Permit Application Clearance Information

Address approval Cleared 1/2/2026 ROSE STEIN-WENDT
Eng Process Fee Ord 176,300 Cleared 1/6/2026 ROSE STEIN-WENDT
Sewer availability Cleared 1/6/2026 ROSE STEIN-WENDT

Contact Information

Contractor Radessen Construction & Design Llc; Lic. No.: 1081788-B       ,
Engineer Mohammadi,, Saeid; Lic. No.: C82330 17412 VENTUTRA BLVD 21      ENCINO, CA 91316

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/16/2026 Not Ready for Inspection ARUTYUN MADATYAN
Footing/Foundation/Slab 3/20/2026 Partial Approval GEVORK IPCHYAN
PLUMBING-Rough 4/1/2026 Partial Approval GEVORK IPCHYAN
Footing/Foundation/Slab 4/9/2026 Approved GEVORK IPCHYAN
BUILDING-Rough-Frame 5/1/2026 Partial Approval GEVORK IPCHYAN
ELECTRICAL-Rough 5/1/2026 Partial Approval GEVORK IPCHYAN
Green Building Rough 5/1/2026 Not Ready for Inspection GEVORK IPCHYAN
ELECTRICAL-Rough 5/11/2026 Approved GEVORK IPCHYAN
Insulation 5/11/2026 Partial Approval GEVORK IPCHYAN
PLUMBING-Rough 5/11/2026 Approved GEVORK IPCHYAN
Floor/Roof Diaphrgm/Shear Wall 5/20/2026 Partial Approval GEVORK IPCHYAN
Rough-Elec/Plmb/HVAC 5/20/2026 Approved GEVORK IPCHYAN
Shower Pan 5/20/2026 Approved GEVORK IPCHYAN
BUILDING-Rough-Frame 5/28/2026 Approved GEVORK IPCHYAN
Drywall Nailing 5/28/2026 Partial Approval GEVORK IPCHYAN
Green Building Rough 5/28/2026 Approved GEVORK IPCHYAN
Insulation 5/28/2026 Approved GEVORK IPCHYAN
Interior/Exterior Lathing 5/28/2026 Partial Approval GEVORK IPCHYAN