15041 W TUBA ST 91345
Certificate Information: 15041 W TUBA ST 91345
- Application / Permit
- 25016-20000-35434
- Plan Check / Job No.
- B25VN35211
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan ** Convert existing 20' x 20' detached garage into ADU per state law
- Permit Issued
- Issued on 1/28/2026
- Issuing Office
- Current Status
- Issued on 1/28/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/3/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 12/8/2025 | KAVIAN REFAHI |
| Corrections Issued | 12/8/2025 | KAVIAN REFAHI |
| Assigned to Zoning Architect | 12/9/2025 | KAVIAN REFAHI |
| Applicant returned to address corrections | 1/22/2026 | KAVIAN REFAHI |
| Plan Check Approved | 1/27/2026 | KAVIAN REFAHI |
| Issued | 1/28/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/7/2026 | MICHAEL BROWN |
| Eng Process Fee Ord 176,300 | Cleared | 1/7/2026 | MICHAEL BROWN |
| Sewer availability | Cleared | 1/7/2026 | MICHAEL BROWN |
| Roof/Waste drainage to street | Cleared | 1/20/2026 | MICHAEL BROWN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/20/2026 | Conditional Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 4/1/2026 | Not Ready for Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 4/1/2026 | Not Ready for Inspection | JENNIFER RABUCHIN |
| PLUMBING-Rough | 4/1/2026 | Corrections Issued | JENNIFER RABUCHIN |
| Sewer | 4/1/2026 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 5/5/2026 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 5/5/2026 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 5/5/2026 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 5/5/2026 | Partial Approval | JENNIFER RABUCHIN |
| HVAC-Rough | 5/12/2026 | Not Ready for Inspection | JOSE AVILA |
| Wood Frame | 5/12/2026 | Partial Approval | JOSE AVILA |
| BUILDING-Rough-Frame | 5/20/2026 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 5/20/2026 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Rough | 5/20/2026 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 5/22/2026 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 5/22/2026 | Approved | JENNIFER RABUCHIN |
| Insulation | 5/22/2026 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 6/2/2026 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 6/2/2026 | Approved | JENNIFER RABUCHIN |