- ePlan: Change of use to existing from (e) 161'3" x 92'4-1/2" (14,651 sq.ft.) manufacturing / office building to new indoor training facility with batting cages and offices / retail area . Interior alterations to building and structural upgrades, all work per engineering
- Permit Issued
- Issued on 3/20/2026
- Issuing Office
- Current Status
- Issued on 3/20/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/26/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 12/11/2025 | RARES BODEA |
| Assigned to Zoning Architect | 12/11/2025 | HAYDON CHAN |
| Corrections Issued | 12/15/2025 | RARES BODEA |
| Quality Review Completed | 12/18/2025 | STEVEN KIM |
| Applicant returned to address corrections | 3/3/2026 | RARES BODEA |
| Plan Check Approved | 3/17/2026 | RARES BODEA |
| Issued | 3/20/2026 | APPLICANT |
Permit Application Clearance Information
| "T" removal | Cleared | 12/22/2025 | ALEX VELA |
| Private street | Cleared | 12/22/2025 | ALEX VELA |
| Sewer availability | Cleared | 1/6/2026 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/7/2026 | DAVID LOPEZ |
| Green Code | Cleared | 1/29/2026 | MICHAEL AYERS |
| Fire Marshal Fire Life Safety | Cleared | 2/6/2026 | ANDREW KO |
| Zoning Plan Check | Cleared | 2/23/2026 | HAYDON CHAN |
| "Q" conditions | Cleared | 2/27/2026 | ALEX VELA |
| DAS Clearance | Cleared | 3/3/2026 | Ricardo Ramirez Solis |
Contact Information
| Architect | Jason, R Herber; Lic. No.: C35679 | , |
| Contractor | Christie Building And Development Inc; Lic. No.: 959374-B | , |
| Engineer | Boranian,, Paul; Lic. No.: S5944 | 26227 VEVA WAY CALABASAS, CA 91302 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Drywall Nailing | 4/3/2026 | Not Ready for Inspection | EDWIN GREGORYONA |
| Wood Frame | 4/3/2026 | Partial Inspection | EDWIN GREGORYONA |
| Wood Frame | 4/14/2026 | Approved | EDWIN GREGORYONA |
| Drywall Nailing | 5/1/2026 | Approved | EDWIN GREGORYONA |
| T-Bar Ceiling | 6/5/2026 | Approved | EDWIN GREGORYONA |