18318-18320 W INDEX ST 91326
Certificate Information: 18318-18320 W INDEX ST 91326
- Application / Permit
- 25016-20000-34118
- Plan Check / Job No.
- B25VN33855
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EX ATTACHED GARAGE INTO ACCESSORY DWELLING UNIT PER GCS 66323(a)(1). ALL WORK PER WFPP.
- Permit Issued
- Issued on 12/12/2025
- Issuing Office
- Valley
- Current Status
- Issued on 12/12/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/18/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 11/24/2025 | HAYATO TSUCHIYA |
| Corrections Issued | 11/24/2025 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 11/26/2025 | APPLICANT |
| Issued | 12/12/2025 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 12/5/2025 | MANUEL TEJADA |
| Address approval | Cleared | 12/8/2025 | JEFF LOREDO |
| Sewer availability | Cleared | 12/8/2025 | JEFF LOREDO |
| Flood clearance | Cleared | 12/9/2025 | SAMSON WONG |
| Eng Process Fee Ord 176,300 | Cleared | 12/12/2025 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/2/2026 | Approved | KRISTEN CAUSEY |
| Footing/Foundation/Slab | 1/2/2026 | Approved | KRISTEN CAUSEY |
| PLUMBING-Rough | 1/8/2026 | Partial Approval | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 1/20/2026 | Not Ready for Inspection | DAVID SCANTLIN |
| ELECTRICAL-Rough | 1/20/2026 | Approved | DAVID SCANTLIN |
| FLOOD-Proofing Certificate | 1/20/2026 | Approved | DAVID SCANTLIN |
| Green Building Rough | 1/20/2026 | Not Ready for Inspection | DAVID SCANTLIN |
| MERV13>=Rough | 1/20/2026 | Not Ready for Inspection | DAVID SCANTLIN |
| PLUMBING-Rough | 1/20/2026 | Approved | DAVID SCANTLIN |
| HVAC-Rough | 1/28/2026 | Approved | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 1/28/2026 | Partial Approval | KRISTEN CAUSEY |
| Insulation | 2/2/2026 | Approved | DAVID SCANTLIN |
| Drywall Nailing | 2/9/2026 | Approved | KRISTEN CAUSEY |
| Shower Pan | 2/9/2026 | Approved | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 3/11/2026 | Approved | DAVID SCANTLIN |
| Final | 3/11/2026 | Corrections Issued | DAVID SCANTLIN |
| Green Building Final | 3/11/2026 | Not Ready for Inspection | DAVID SCANTLIN |
| Green Building Rough | 3/11/2026 | Approved | DAVID SCANTLIN |
| MERV13>=Final | 3/11/2026 | Approved | DAVID SCANTLIN |
| MERV13>=Rough | 3/11/2026 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 3/11/2026 | SGSOV Approved | DAVID SCANTLIN |
| Smoke Detectors | 3/11/2026 | Approved | DAVID SCANTLIN |
| Final | 4/1/2026 | Not Ready for Inspection | DAVID SCANTLIN |
| Green Building Final | 4/1/2026 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 4/7/2026 | Not Ready for Inspection | DAVID SCANTLIN |
| Special/Order Compliance | 4/7/2026 | Approved | DAVID SCANTLIN |