20431 W GRESHAM ST 91306
Certificate Information: 20431 W GRESHAM ST 91306
- Application / Permit
- 25016-20000-34011
- Plan Check / Job No.
- B25VN33735
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. Conversion of (E) Detached Garage to (N) ADU per GC 66323(a)(1)
- Permit Issued
- Issued on 1/20/2026
- Issuing Office
- Current Status
- Issued on 1/20/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/18/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2025 | MOHAMMAD ESMAILI |
| Corrections Issued | 11/22/2025 | MOHAMMAD ESMAILI |
| Plan Check Approved | 1/8/2026 | MOHAMMAD ESMAILI |
| Issued | 1/20/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 12/12/2025 | JESUS CISNEROS |
| Sewer availability | Cleared | 12/12/2025 | JESUS CISNEROS |
| Eng Process Fee Ord 176,300 | Cleared | 12/18/2025 | JESUS CISNEROS |
| Construction near power lines | Cleared | 1/7/2026 | GEVORK KARAPETYAN |
| Construction within easement | Cleared | 1/7/2026 | GEVORK KARAPETYAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mohammadi,, Saeid; Lic. No.: C82330 | 17412 VENTUTRA BLVD 21 ENCINO, CA 91316 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/22/2026 | Conditional Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 1/30/2026 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Rough | 1/30/2026 | Partial Approval | ARUTYUN MADATYAN |
| Sewer | 1/30/2026 | Approved | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/24/2026 | Partial Approval | JEFFREY HARTLINE |
| Rough-Elec/Plmb/HVAC | 2/24/2026 | Not Ready for Inspection | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 3/6/2026 | Partial Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 3/6/2026 | Approved | CHRIS CHRISTENSEN |
| HVAC-Rough | 3/6/2026 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 3/6/2026 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 3/16/2026 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 3/16/2026 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 3/16/2026 | Partial Approval | CHRIS CHRISTENSEN |
| Drywall Nailing | 3/24/2026 | Approved | CHRIS CHRISTENSEN |
| Shower Pan | 5/7/2026 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 5/21/2026 | Approved | CHRISTOPHER WILSON |
| Pre-Inspection | 5/21/2026 | Partial Inspection | CHRISTOPHER WILSON |