1622 N ORANGE GROVE AVE 90046
Certificate Information: 1622 N ORANGE GROVE AVE 90046
- Application / Permit
- 25016-20000-33774
- Plan Check / Job No.
- B25VN33536
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL AND REFRAME TO SFD, ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 3/31/2026
- Issuing Office
- Valley
- Current Status
- Issued on 3/31/2026
Permit Application Status History
| Submitted | 11/14/2025 | APPLICANT |
| Assigned to Zoning Architect | 11/20/2025 | LY CHEA |
| Assigned to Plan Check Engineer | 11/25/2025 | RARES BODEA |
| Corrections Issued | 12/4/2025 | RARES BODEA |
| Quality Review Completed | 12/9/2025 | STEVEN KIM |
| Building Plans Picked Up | 12/12/2025 | APPLICANT |
| Plan Check Approved | 3/26/2026 | RARES BODEA |
| Issued | 3/31/2026 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/19/2025 | ROSE STEIN-WENDT |
| Sewer availability | Cleared | 12/19/2025 | ROSE STEIN-WENDT |
| Eng Process Fee Ord 176,300 | Cleared | 12/26/2025 | ROSE STEIN-WENDT |
| HPOZ | Cleared | 3/4/2026 | JORGE RUIZ |
| Miscellaneous | Cleared | 3/9/2026 | TERRY PHAN |
| Zoning Plan Check | Cleared | 3/12/2026 | LY CHEA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Barragan,, Pedro; Lic. No.: C90531 | 4954 TOPANGA CYN BLVD WOODLAND HILLS, CA 91364 |
Inspector Information
| No Data Available. |
Pending Inspections
| Interior/Exterior Lathing | 7/24/2026 |
Inspection Request History
| Gas Test | 4/29/2026 | Approved | ROY SPAULDING |
| PLUMBING-Rough | 4/29/2026 | Approved | ROY SPAULDING |
| Footing/Foundation/Slab | 5/22/2026 | Corrections Issued | ROY SPAULDING |
| ELECTRICAL-Rough | 5/27/2026 | Not Ready for Inspection | ROY SPAULDING |
| Footing/Foundation/Slab | 5/27/2026 | Approved | ROY SPAULDING |
| BUILDING-Rough-Frame | 6/17/2026 | Not Ready for Inspection | ROY SPAULDING |
| ELECTRICAL-Rough | 6/17/2026 | Corrections Issued | ROY SPAULDING |
| HVAC-Rough | 6/17/2026 | Corrections Issued | ROY SPAULDING |
| BUILDING-Rough-Frame | 6/23/2026 | Partial Approval | ROY SPAULDING |
| ELECTRICAL-Rough | 6/23/2026 | Approved | ROY SPAULDING |
| HVAC-Rough | 6/23/2026 | Approved | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 6/25/2026 | Corrections Issued | ROY SPAULDING |
| Insulation | 6/25/2026 | Not Ready for Inspection | ROY SPAULDING |
| ELECTRICAL-Rough | 6/29/2026 | Approved | ROY SPAULDING |
| Insulation | 6/29/2026 | Partial Approval | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 7/2/2026 | Approved | ROY SPAULDING |
| Drywall Nailing | 7/13/2026 | Approved | ROY SPAULDING |