149 1/2 E 78TH ST 90003

Certificate Information: 149 1/2 E 78TH ST 90003

Application / Permit
25016-20000-33579
Plan Check / Job No.
B25VN33301
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN. FIRE DAMAGE REPAIR TO EXISTING SFD
Permit Issued
Issued on 1/14/2026
Issuing Office
Current Status
Issued on 1/14/2026

Permit Application Status History

Submitted 11/13/2025 APPLICANT
Assigned to Plan Check Engineer 11/17/2025 FERNANDO FLORES
Corrections Issued 11/18/2025 FERNANDO FLORES
Applicant returned to address corrections 12/16/2025 FERNANDO FLORES
Plan Check Approved 12/19/2025 FERNANDO FLORES
Issued 1/14/2026 APPLICANT

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Ikon Builders Inc; Lic. No.: 966760-B       ,
Engineer Hansen,, Hans Christian; Lic. No.: C80546 12831 MALENA DR      SANTA ANA, CA 92705

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 2/23/2026 Not Ready for Inspection JOHN QUINTANILLA
ELECTRICAL-Rough 2/23/2026 Not Ready for Inspection JOHN QUINTANILLA
PLUMBING-Rough 2/23/2026 Corrections Issued JOHN QUINTANILLA
ELECTRICAL-Rough 3/6/2026 Corrections Issued JOHN QUINTANILLA
Gas Test 3/6/2026 Approved JOHN QUINTANILLA
HVAC-Rough 3/6/2026 Corrections Issued JOHN QUINTANILLA
PLUMBING-Rough 3/6/2026 Corrections Issued JOHN QUINTANILLA
BUILDING-Rough-Frame 3/18/2026 No Access for Inspection JOHN QUINTANILLA
ELECTRICAL-Rough 3/18/2026 No Access for Inspection JOHN QUINTANILLA
HVAC-Rough 3/18/2026 No Access for Inspection JOHN QUINTANILLA
Interior/Exterior Lathing 3/18/2026 No Access for Inspection JOHN QUINTANILLA
PLUMBING-Rough 3/18/2026 No Access for Inspection JOHN QUINTANILLA
BUILDING-Rough-Frame 3/24/2026 Partial Inspection JOHN QUINTANILLA
ELECTRICAL-Rough 3/24/2026 Partial Inspection JOHN QUINTANILLA
HVAC-Rough 3/24/2026 Partial Inspection JOHN QUINTANILLA
PLUMBING-Rough 3/24/2026 Partial Inspection JOHN QUINTANILLA
BUILDING-Rough-Frame 3/26/2026 Approved JOHN QUINTANILLA
ELECTRICAL-Rough 3/26/2026 Approved JOHN QUINTANILLA
PLUMBING-Rough 3/26/2026 Approved JOHN QUINTANILLA
Insulation 4/7/2026 Approved JOHN QUINTANILLA
Interior/Exterior Lathing 4/7/2026 Approved JOHN QUINTANILLA
Drywall Nailing 4/17/2026 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 4/28/2026 Approved ALEX COLIN