16102 W MAYALL ST 91343

Certificate Information: 16102 W MAYALL ST 91343

Application / Permit
25016-20000-32757
Plan Check / Job No.
B25VN32262
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EX DETACHED GARAGE + ADDITION INTO ACCESSORY DWELLING UNIT PER GCS 66323(a)(2). ALL WORK PER ENGINEERING
Permit Issued
Issued on 12/1/2025
Issuing Office
Current Status
CofO in Progress on 5/26/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/3/2025 APPLICANT
Assigned to Plan Check Engineer 11/7/2025 HAYATO TSUCHIYA
Corrections Issued 11/7/2025 HAYATO TSUCHIYA
Building Plans Picked Up 11/10/2025 APPLICANT
Applicant returned to address corrections 11/24/2025 LUISANGEL VALENZUELA
Applicant returned to address corrections 12/1/2025 ISIS ARGUETA
Issued 12/1/2025 APPLICANT
CofO in Progress 5/26/2026 CHRISTOPHER ROJAS

Permit Application Clearance Information

Address approval Cleared 11/12/2025 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 11/12/2025 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 11/24/2025 LEE GUILBEAUX
Sewer availability Cleared 11/24/2025 LEE GUILBEAUX
Construction within easement Cleared 11/26/2025 WALTER RAMIREZ
Grading Pre-Inspection Cleared 12/1/2025 ALEXANDER HELFER

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 12/3/2025 Partial Approval CHRISTOPHER ROJAS
Footing/Foundation/Slab 12/8/2025 Approved CHRISTOPHER ROJAS
Deputy Drilled-In Anchors 12/9/2025 Conditional Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 12/15/2025 Corrections Issued CRAIG DAVIS
Wood Frame 12/15/2025 Corrections Issued CRAIG DAVIS
BUILDING-Rough-Frame 12/18/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 12/18/2025 Partial Approval CHRISTOPHER ROJAS
Green Building Rough 12/18/2025 Not Ready for Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 12/26/2025 Corrections Issued MICHEL ABAJAN
Green Building Rough 12/26/2025 Not Ready for Inspection MICHEL ABAJAN
Interior/Exterior Lathing 12/26/2025 Approved MICHEL ABAJAN
Rough-Elec/Plmb/HVAC 12/26/2025 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 12/29/2025 Approved CHRISTOPHER ROJAS
Green Building Rough 12/29/2025 Approved CHRISTOPHER ROJAS
HVAC-Rough 12/29/2025 Approved CHRISTOPHER ROJAS
Insulation 1/27/2026 Approved KIRK SANDERS
Shower Pan 1/27/2026 Approved KIRK SANDERS
Drywall Nailing 2/5/2026 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 2/5/2026 Corrections Issued CHRISTOPHER ROJAS
Interior/Exterior Lathing 2/10/2026 Partial Approval CHRISTOPHER ROJAS
Gas Test 4/15/2026 Partial Approval MICHAEL CORTEZ
Sewer 4/15/2026 Approved MICHAEL CORTEZ
Underground Mechanical 4/15/2026 Partial Approval MICHAEL CORTEZ
ELECTRICAL-Final 5/14/2026 Corrections Issued CHRISTOPHER ROJAS
Final 5/14/2026 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Final 5/14/2026 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Final 5/14/2026 Corrections Issued CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 5/14/2026 SGSOV Approved CHRISTOPHER ROJAS
Service/Power Release 5/14/2026 Approved CHRISTOPHER ROJAS
Smoke Detectors 5/14/2026 Corrections Issued CHRISTOPHER ROJAS
Final 5/20/2026 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 5/20/2026 Approved CHRISTOPHER ROJAS
Smoke Detectors 5/20/2026 Approved CHRISTOPHER ROJAS
Final 5/26/2026 OK to Issue CofO CHRISTOPHER ROJAS