10253 N RUSSETT AVE 91040

Certificate Information: 10253 N RUSSETT AVE 91040

Application / Permit
25016-20000-32743
Plan Check / Job No.
B25VN32238
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 66323(A)(2)
Permit Issued
Issued on 12/16/2025
Issuing Office
Valley
Current Status
CofO Issued on 5/15/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/3/2025 APPLICANT
Assigned to Plan Check Engineer 11/7/2025 JEROME MAGAT PALMA
Corrections Issued 11/8/2025 JEROME MAGAT PALMA
Building Plans Picked Up 11/17/2025 APPLICANT
Applicant returned to address corrections 12/1/2025 HAYATO TSUCHIYA
Plan Check Approved 12/16/2025 ALEC MOUSAKHANIAN
Issued 12/16/2025 APPLICANT
CofO in Progress 4/21/2026 DAVID ANDERSON
Permit Finaled 5/15/2026 RUBEN SALAS
CofO Issued 5/15/2026 RUBEN SALAS
Permit Finaled 5/15/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/5/2025 DERRICK MAGEE
Eng Process Fee Ord 176,300 Cleared 12/5/2025 DERRICK MAGEE
Sewer availability Cleared 12/5/2025 DERRICK MAGEE

Contact Information

Contractor Owner-Builder       ,
Engineer Hagopyan,, Edmond; Lic. No.: C80143 3300 FOOTHILL BLVD   # 8601    GLENDALE, CA 91214

Inspector Information

MATTHEW NELSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/3/2026 Approved DAVID ANDERSON
Footing/Foundation/Slab 2/3/2026 Approved DAVID ANDERSON
PLUMBING-Rough 2/3/2026 Partial Approval DAVID ANDERSON
BUILDING-Rough-Frame 2/12/2026 Approved DAVID ANDERSON
ELECTRICAL-Rough 2/12/2026 Approved DAVID ANDERSON
Green Building Rough 2/12/2026 Approved DAVID ANDERSON
HVAC-Rough 2/12/2026 Approved DAVID ANDERSON
PLUMBING-Rough 2/12/2026 Approved DAVID ANDERSON
Insulation 2/17/2026 Corrections Issued DAVID ANDERSON
Interior/Exterior Lathing 2/17/2026 Partial Approval DAVID ANDERSON
Insulation 2/19/2026 Approved DAVID ANDERSON
Drywall Nailing 2/23/2026 Approved DAVID ANDERSON
Shower Pan 2/23/2026 Approved DAVID ANDERSON
Underground Mechanical 3/16/2026 Approved DAVID ANDERSON
Final 4/9/2026 Corrections Issued DAVID ANDERSON
Green Building Final 4/9/2026 Not Ready for Inspection DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 4/9/2026 SGSOV Approved DAVID ANDERSON
Service/Power Release 4/9/2026 Not Ready for Inspection DAVID ANDERSON
Smoke Detectors 4/9/2026 Approved DAVID ANDERSON
Final 4/15/2026 OK to Issue CofO DAVID ANDERSON
Green Building Final 4/15/2026 Approved DAVID ANDERSON