13913 W GARBER ST 91331

Certificate Information: 13913 W GARBER ST 91331

Application / Permit
25016-20000-32595
Plan Check / Job No.
B25VN32123
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION TO AND CONVERT DETACHED GARAGE / STORAGE ROOM TO ACCESSORY DWELLING UNIT PER GCS 66323(A)(2), REROOF. ALL WORK PER WFPP.
Permit Issued
Issued on 12/2/2025
Issuing Office
Current Status
Issued on 12/2/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/31/2025 APPLICANT
Assigned to Plan Check Engineer 11/7/2025 JEROME MAGAT PALMA
Corrections Issued 11/11/2025 JEROME MAGAT PALMA
Building Plans Picked Up 11/13/2025 APPLICANT
Plan Check Approved 12/2/2025 MINA HABILI
Issued 12/2/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 11/21/2025 DERRICK MAGEE
Eng Process Fee Ord 176,300 Cleared 11/21/2025 DERRICK MAGEE
Roof/Waste drainage to street Cleared 11/21/2025 DERRICK MAGEE
Sewer availability Cleared 11/21/2025 DERRICK MAGEE
ZA Case Cleared 11/26/2025 DAVID URITA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/27/2026 Approved OGANES TARAKHCHYAN
Wood Frame 3/16/2026 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 3/17/2026 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 3/18/2026 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 3/24/2026 Not Ready for Inspection JEFFREY PARD
Interior/Exterior Lathing 3/24/2026 Approved JEFFREY PARD
ELECTRICAL-Rough 4/2/2026 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 4/2/2026 Approved OGANES TARAKHCHYAN
Shower Pan 4/2/2026 Approved OGANES TARAKHCHYAN
HVAC-Rough 4/7/2026 Approved OGANES TARAKHCHYAN
Wood Frame 4/7/2026 Approved OGANES TARAKHCHYAN
Insulation 4/9/2026 Approved OGANES TARAKHCHYAN
Drywall Nailing 4/13/2026 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 4/16/2026 Approved OGANES TARAKHCHYAN
Pre-Inspection 4/16/2026 Approved OGANES TARAKHCHYAN
Special/Order Compliance 4/21/2026 Partial Inspection DAVID MATSON
BUILDING-Rough-Frame 6/1/2026 Approved OGANES TARAKHCHYAN
Final 6/1/2026 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Final 6/1/2026 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Rough 6/1/2026 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 6/1/2026 SGSOV Not Ready OGANES TARAKHCHYAN
Smoke Detectors 6/1/2026 Approved OGANES TARAKHCHYAN