9708 N KESTER AVE 91343

Certificate Information: 9708 N KESTER AVE 91343

Application / Permit
25016-20000-32593
Plan Check / Job No.
B25VN32121
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan Convert (E) Guest House Into a (N) ADU per GC 66323(a)(1)
Permit Issued
Issued on 5/2/2026
Issuing Office
Current Status
CofO in Progress on 6/23/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/31/2025 APPLICANT
Assigned to Plan Check Engineer 11/4/2025 JOHN MESIAS
Corrections Issued 11/4/2025 JOHN MESIAS
Applicant returned to address corrections 3/7/2026 JOHN MESIAS
Applicant returned to address corrections 4/1/2026 JOHN MESIAS
Plan Check Approved 4/2/2026 JOHN MESIAS
Issued 5/2/2026 APPLICANT
CofO in Progress 6/23/2026 JENNIFER RABUCHIN

Permit Application Clearance Information

Address approval Cleared 1/14/2026 BIAINA HARITUNIAN
Sewer availability Cleared 1/14/2026 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 1/21/2026 BIAINA HARITUNIAN
Construction near power lines Cleared 2/21/2026 GEVORK KARAPETYAN

Contact Information

Contractor Fiero Development; Lic. No.: 806761-B       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Final 5/6/2026 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 5/6/2026 Approved JENNIFER RABUCHIN
HVAC-Final 5/6/2026 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 5/6/2026 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Final 5/13/2026 Corrections Issued JENNIFER RABUCHIN
Final 5/13/2026 Corrections Issued JENNIFER RABUCHIN
Gas Test 5/13/2026 Approved JENNIFER RABUCHIN
Green Building Final 5/13/2026 Approved JENNIFER RABUCHIN
HVAC-Final 5/13/2026 Approved JENNIFER RABUCHIN
PLUMBING-Final 5/13/2026 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 5/13/2026 SGSOV Not Ready JENNIFER RABUCHIN
Smoke Detectors 5/13/2026 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 6/10/2026 Approved JENNIFER RABUCHIN
Final 6/10/2026 OK to Issue CofO JENNIFER RABUCHIN
PLUMBING-Final 6/10/2026 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 6/10/2026 SGSOV Approved JENNIFER RABUCHIN