9131 N WOODLEY AVE 91343

Certificate Information: 9131 N WOODLEY AVE 91343

Application / Permit
25016-20000-32533
Plan Check / Job No.
B25VN32057
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: Convert existing detached garage to ADU per GCS 66323 (a)(1) and engineering done per WFPP.
Permit Issued
Issued on 12/8/2025
Issuing Office
Current Status
Issued on 12/8/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/3/2025 APPLICANT
Assigned to Plan Check Engineer 11/5/2025 BEHROUZ KHOKHAR
Corrections Issued 11/6/2025 BEHROUZ KHOKHAR
Plan Check Approved 11/22/2025 CAROLEAN BASMA
Issued 12/8/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 11/18/2025 JEFF LOREDO
Sewer availability Cleared 11/18/2025 JEFF LOREDO
Eng Process Fee Ord 176,300 Cleared 11/19/2025 JEFF LOREDO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/13/2026 Conditional Approval JOAQUIN GREENOUGH
Underground Mechanical 1/16/2026 Corrections Issued MICHAEL CORTEZ
Underground Mechanical 1/21/2026 Approved WAYNE REGESTER
Deputy Drilled-In Anchors 1/23/2026 Conditional Approval GAREN HAYRAPETYAN
Footing/Foundation/Slab 1/26/2026 Approved GAREN HAYRAPETYAN
Sewer 1/26/2026 Approved GAREN HAYRAPETYAN
BUILDING-Rough-Frame 3/6/2026 Not Ready for Inspection KIRK SANDERS
ELECTRICAL-Final 3/6/2026 Corrections Issued KIRK SANDERS
ELECTRICAL-Rough 3/6/2026 Corrections Issued KIRK SANDERS
Green Building Rough 3/6/2026 Corrections Issued KIRK SANDERS
PLUMBING-Rough 3/6/2026 Approved KIRK SANDERS
BUILDING-Rough-Frame 3/11/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 3/11/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 3/11/2026 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Rough 3/11/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 3/17/2026 Corrections Issued KIRK SANDERS
ELECTRICAL-Rough 3/17/2026 Partial Approval KIRK SANDERS
Green Building Rough 3/17/2026 Not Ready for Inspection KIRK SANDERS
Shower Pan 3/17/2026 Not Ready for Inspection KIRK SANDERS
BUILDING-Rough-Frame 4/22/2026 No Access for Inspection RUBEN SALAS
ELECTRICAL-Rough 4/22/2026 No Access for Inspection RUBEN SALAS
Green Building Rough 4/22/2026 No Access for Inspection RUBEN SALAS
Interior/Exterior Lathing 4/22/2026 No Access for Inspection RUBEN SALAS
BUILDING-Rough-Frame 4/27/2026 Not Ready for Inspection VINCENT HANLEY
ELECTRICAL-Rough 4/27/2026 Not Ready for Inspection VINCENT HANLEY
Green Building Rough 4/27/2026 Approved VINCENT HANLEY
Interior/Exterior Lathing 4/27/2026 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 5/19/2026 Approved MICHAEL CORTEZ
ELECTRICAL-Rough 5/19/2026 Approved MICHAEL CORTEZ
HVAC-Rough 5/19/2026 Approved MICHAEL CORTEZ
Insulation 5/26/2026 Corrections Issued MICHAEL CORTEZ
Insulation 6/5/2026 Approved JENNIFER RABUCHIN
Drywall Nailing 6/11/2026 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 6/11/2026 Approved MICHAEL CORTEZ