8819 N ENCINO AVE 91325

Certificate Information: 8819 N ENCINO AVE 91325

Application / Permit
25016-20000-31520
Plan Check / Job No.
B25VN31048
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) ALQ WITH INTERIOR REMODEL TO ACCESSORY DWELLING UNIT PER GC 66323(a)(1) ALL WORK PER WFPP NFPA 13D REQUIRED THROUGHOUT
Permit Issued
Issued on 11/13/2025
Issuing Office
Current Status
CofO Issued on 5/21/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/22/2025 APPLICANT
Assigned to Plan Check Engineer 10/28/2025 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 10/29/2025 SEWADA ZADOORIAN MILAGARDI
Building Plans Picked Up 10/31/2025 APPLICANT
Plan Check Approved 11/7/2025 MOHAMMAD ESMAILI
Issued 11/13/2025 APPLICANT
CofO in Progress 4/27/2026 CHRISTOPHER ROJAS
CofO Issued 5/21/2026 RUBEN SALAS
Permit Finaled 5/21/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/31/2025 WALLIE JONG
Sewer availability Cleared 10/31/2025 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 11/3/2025 WALLIE JONG
Hydrant and Access approval Cleared 11/5/2025 GILBERT URREA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 11/24/2025 Approved KEVIN BERBERYAN
HVAC-Rough 11/24/2025 Corrections Issued KEVIN BERBERYAN
PLUMBING-Rough 11/24/2025 Corrections Issued KEVIN BERBERYAN
Pre-Inspection 11/24/2025 Partial Inspection KEVIN BERBERYAN
PLUMBING-Rough 3/24/2026 Partial Approval CHRISTOPHER ROJAS
HVAC-Rough 3/26/2026 Corrections Issued CHRISTOPHER ROJAS
Interior/Exterior Lathing 3/26/2026 Approved CHRISTOPHER ROJAS
Shower Pan 3/26/2026 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 4/7/2026 Approved CHRISTOPHER ROJAS
Final 4/7/2026 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Final 4/7/2026 Corrections Issued CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 4/7/2026 SGSOV Approved CHRISTOPHER ROJAS
Smoke Detectors 4/7/2026 Not Ready for Inspection CHRISTOPHER ROJAS
Final 4/10/2026 Corrections Issued CHRISTOPHER ROJAS
Smoke Detectors 4/10/2026 Approved CHRISTOPHER ROJAS
Final 4/17/2026 Corrections Issued CHRISTOPHER ROJAS
Final 4/27/2026 OK to Issue CofO CHRISTOPHER ROJAS