1169 E 48TH ST #4 90011
Certificate Information: 1169 E 48TH ST #4 90011
- Application / Permit
- 25016-20000-30921
- Plan Check / Job No.
- B25VN30483
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- ePlan: Convert portion of unit #3 into an ADU per LAMC 12.22 A.33 (c) and (e).
- Permit Issued
- Issued on 2/27/2026
- Issuing Office
- Current Status
- Issued on 2/27/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/16/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 10/20/2025 | CAROLEAN BASMA |
| Corrections Issued | 10/21/2025 | CAROLEAN BASMA |
| Applicant returned to address corrections | 1/29/2026 | CAROLEAN BASMA |
| Applicant returned to address corrections | 2/3/2026 | KAVIAN REFAHI |
| Applicant returned to address corrections | 2/25/2026 | CAROLEAN BASMA |
| Plan Check Approved | 2/27/2026 | CAROLEAN BASMA |
| Issued | 2/27/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/17/2026 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 2/3/2026 | ERIK BEASLEY |
| Sewer availability | Cleared | 2/26/2026 | JESUS CISNEROS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Drywall Nailing | 4/22/2026 | Conditional Approval | DARRYL ARNOLD |
| Insulation | 4/22/2026 | Conditional Approval | DARRYL ARNOLD |
| Smoke Detectors | 4/22/2026 | Corrections Issued | DARRYL ARNOLD |
| Wood Frame | 4/22/2026 | Conditional Approval | DARRYL ARNOLD |
| Drywall Nailing | 5/1/2026 | Partial Approval | PAUL BAZERKANIAN |
| Final | 5/13/2026 | Partial Inspection | ALFREDO LOPEZ |
| Final | 5/15/2026 | Partial Inspection | ALFREDO LOPEZ |
| Pre-Inspection | 5/15/2026 | Not Ready for Inspection | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 5/15/2026 | SGSOV Approved | ALFREDO LOPEZ |
| Smoke Detectors | 5/15/2026 | Not Ready for Inspection | ALFREDO LOPEZ |
| Verify Rec and Parks Fee Memo | 5/15/2026 | Not Ready for Inspection | ALFREDO LOPEZ |
| Wood Frame | 5/15/2026 | Approved | ALFREDO LOPEZ |