7112-7114 N GATESHEAD WAY 91307
Certificate Information: 7112-7114 N GATESHEAD WAY 91307
- Application / Permit
- 25016-20000-30689
- Plan Check / Job No.
- B25VN30244
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERTING EXISTING ATTACHED GARAGE TO ADU PER GC 66323(a)(1)
- Permit Issued
- Issued on 11/6/2025
- Issuing Office
- Current Status
- CofO Issued on 6/16/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/14/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 10/17/2025 | CRYSTEL MAALOUF |
| Corrections Issued | 10/18/2025 | CRYSTEL MAALOUF |
| Plan Check Approved | 10/24/2025 | CRYSTEL MAALOUF |
| Issued | 11/6/2025 | APPLICANT |
| CofO in Progress | 6/9/2026 | JEFFREY HARTLINE |
| Permit Finaled | 6/16/2026 | JOHN JANSON |
| CofO Issued | 6/16/2026 | JOHN JANSON |
| Permit Finaled | 6/16/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 10/20/2025 | ABEL CASILLAS |
| Eng Process Fee Ord 176,300 | Cleared | 10/20/2025 | ABEL CASILLAS |
| Sewer availability | Cleared | 10/20/2025 | ABEL CASILLAS |
| Grading Pre-Inspection | Cleared | 10/21/2025 | ALEXANDER HELFER |
Contact Information
| Contractor | Adar Builders Inc; Lic. No.: 1051859-B | , |
| Engineer | Mohammadi,, Saeid; Lic. No.: C82330 | 17412 VENTUTRA BLVD 21 ENCINO, CA 91316 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/14/2025 | Conditional Approval | HENRY KIM |
| Excavation/Setback/Form/Re-Bar | 11/18/2025 | Approved | JEFFREY HARTLINE |
| Underground Mechanical | 11/18/2025 | Approved | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 12/5/2025 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 12/5/2025 | Approved | CHRIS CHRISTENSEN |
| HVAC-Rough | 12/5/2025 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 12/5/2025 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 12/19/2025 | Partial Approval | CHRIS CHRISTENSEN |
| HVAC-Rough | 1/7/2026 | Corrections Issued | CHRIS CHRISTENSEN |
| Deputy Wood Construction | 1/16/2026 | Conditional Approval | CHRIS CHRISTENSEN |
| HVAC-Rough | 1/16/2026 | Approved | CHRIS CHRISTENSEN |
| Insulation | 1/16/2026 | Conditional Approval | CHRIS CHRISTENSEN |
| Wood Frame | 1/16/2026 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 1/27/2026 | Approved | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 2/17/2026 | Approved | CHRIS CHRISTENSEN |
| Shower Pan | 2/17/2026 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 4/3/2026 | SGSOV Not Ready | CHRIS CHRISTENSEN |
| Special/Order Compliance | 4/6/2026 | Corrections Issued | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 4/23/2026 | Approved | CHRIS CHRISTENSEN |
| Final | 4/23/2026 | Corrections Issued | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 4/23/2026 | SGSOV Not Ready | CHRIS CHRISTENSEN |
| Smoke Detectors | 4/23/2026 | Approved | CHRIS CHRISTENSEN |
| Final | 5/20/2026 | Corrections Issued | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 5/20/2026 | SGSOV Not Ready | CHRIS CHRISTENSEN |
| Service/Power Release | 5/20/2026 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Final | 5/27/2026 | Corrections Issued | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 5/27/2026 | SGSOV Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 5/27/2026 | Not Required | CHRIS CHRISTENSEN |
| Final | 6/8/2026 | OK to Issue CofO | JEFFREY HARTLINE |
| Service/Power Release | 6/8/2026 | Approved | JEFFREY HARTLINE |