7112-7114 N GATESHEAD WAY 91307

Certificate Information: 7112-7114 N GATESHEAD WAY 91307

Application / Permit
25016-20000-30689
Plan Check / Job No.
B25VN30244
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERTING EXISTING ATTACHED GARAGE TO ADU PER GC 66323(a)(1)
Permit Issued
Issued on 11/6/2025
Issuing Office
Current Status
CofO Issued on 6/16/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/14/2025 APPLICANT
Assigned to Plan Check Engineer 10/17/2025 CRYSTEL MAALOUF
Corrections Issued 10/18/2025 CRYSTEL MAALOUF
Plan Check Approved 10/24/2025 CRYSTEL MAALOUF
Issued 11/6/2025 APPLICANT
CofO in Progress 6/9/2026 JEFFREY HARTLINE
Permit Finaled 6/16/2026 JOHN JANSON
CofO Issued 6/16/2026 JOHN JANSON
Permit Finaled 6/16/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 10/20/2025 ABEL CASILLAS
Eng Process Fee Ord 176,300 Cleared 10/20/2025 ABEL CASILLAS
Sewer availability Cleared 10/20/2025 ABEL CASILLAS
Grading Pre-Inspection Cleared 10/21/2025 ALEXANDER HELFER

Contact Information

Contractor Adar Builders Inc; Lic. No.: 1051859-B       ,
Engineer Mohammadi,, Saeid; Lic. No.: C82330 17412 VENTUTRA BLVD 21      ENCINO, CA 91316

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/14/2025 Conditional Approval HENRY KIM
Excavation/Setback/Form/Re-Bar 11/18/2025 Approved JEFFREY HARTLINE
Underground Mechanical 11/18/2025 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 12/5/2025 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Rough 12/5/2025 Approved CHRIS CHRISTENSEN
HVAC-Rough 12/5/2025 Not Ready for Inspection CHRIS CHRISTENSEN
PLUMBING-Rough 12/5/2025 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 12/19/2025 Partial Approval CHRIS CHRISTENSEN
HVAC-Rough 1/7/2026 Corrections Issued CHRIS CHRISTENSEN
Deputy Wood Construction 1/16/2026 Conditional Approval CHRIS CHRISTENSEN
HVAC-Rough 1/16/2026 Approved CHRIS CHRISTENSEN
Insulation 1/16/2026 Conditional Approval CHRIS CHRISTENSEN
Wood Frame 1/16/2026 Approved CHRIS CHRISTENSEN
Drywall Nailing 1/27/2026 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 2/17/2026 Approved CHRIS CHRISTENSEN
Shower Pan 2/17/2026 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 4/3/2026 SGSOV Not Ready CHRIS CHRISTENSEN
Special/Order Compliance 4/6/2026 Corrections Issued JEFFREY HARTLINE
BUILDING-Rough-Frame 4/23/2026 Approved CHRIS CHRISTENSEN
Final 4/23/2026 Corrections Issued CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 4/23/2026 SGSOV Not Ready CHRIS CHRISTENSEN
Smoke Detectors 4/23/2026 Approved CHRIS CHRISTENSEN
Final 5/20/2026 Corrections Issued CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 5/20/2026 SGSOV Not Ready CHRIS CHRISTENSEN
Service/Power Release 5/20/2026 Not Ready for Inspection CHRIS CHRISTENSEN
Final 5/27/2026 Corrections Issued CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 5/27/2026 SGSOV Approved CHRIS CHRISTENSEN
Service/Power Release 5/27/2026 Not Required CHRIS CHRISTENSEN
Final 6/8/2026 OK to Issue CofO JEFFREY HARTLINE
Service/Power Release 6/8/2026 Approved JEFFREY HARTLINE