10498-10500 N VENA AVE 91331

Certificate Information: 10498-10500 N VENA AVE 91331

Application / Permit
25016-20000-30656
Plan Check / Job No.
B25VN30211
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN CONVERT EXISTING ATTACHED GARAGE TO JADU per GCS 66323(a)(1) and 66333
Permit Issued
Issued on 12/13/2025
Issuing Office
Current Status
CofO Issued on 6/23/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/14/2025 APPLICANT
Assigned to Plan Check Engineer 10/17/2025 MINA HABILI
Corrections Issued 10/17/2025 MINA HABILI
Applicant returned to address corrections 12/1/2025 MINA HABILI
Plan Check Approved 12/4/2025 MINA HABILI
Issued 12/13/2025 APPLICANT
CofO in Progress 5/29/2026 JENNIFER RABUCHIN
No Progress 6/8/2026 JOSE AVILA
CofO in Progress 6/8/2026 JOSE AVILA
Permit Finaled 6/23/2026 RUBEN SALAS
CofO Issued 6/23/2026 RUBEN SALAS
Permit Finaled 6/23/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/23/2025 JEFF LOREDO
Sewer availability Cleared 10/23/2025 JEFF LOREDO
Eng Process Fee Ord 176,300 Cleared 10/24/2025 JEFF LOREDO

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/9/2026 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 1/27/2026 Approved JENNIFER RABUCHIN
Special/Order Compliance 1/27/2026 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 2/9/2026 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 2/9/2026 Approved JENNIFER RABUCHIN
Green Building Rough 2/9/2026 Corrections Issued JENNIFER RABUCHIN
Insulation 2/9/2026 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 2/9/2026 Approved JENNIFER RABUCHIN
Special/Order Compliance 2/9/2026 Partial Inspection JOSE AVILA
BUILDING-Rough-Frame 2/23/2026 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 2/23/2026 Corrections Issued JENNIFER RABUCHIN
Final 2/23/2026 Corrections Issued JENNIFER RABUCHIN
Green Building Final 2/23/2026 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 2/23/2026 Approved JENNIFER RABUCHIN
HVAC-Final 2/23/2026 Not Ready for Inspection JENNIFER RABUCHIN
Interior/Exterior Lathing 2/23/2026 Approved JENNIFER RABUCHIN
MERV13>=Final 2/23/2026 Approved JENNIFER RABUCHIN
MERV13>=Rough 2/23/2026 Approved JENNIFER RABUCHIN
METHANE-Final 2/23/2026 Approved JENNIFER RABUCHIN
METHANE-Rough 2/23/2026 Approved JENNIFER RABUCHIN
PLUMBING-Final 2/23/2026 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 2/23/2026 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 2/23/2026 Not Ready for Inspection JENNIFER RABUCHIN
Special/Order Compliance 2/23/2026 Approved JENNIFER RABUCHIN
Final 4/30/2026 Corrections Issued JENNIFER RABUCHIN
Green Building Final 4/30/2026 Corrections Issued JENNIFER RABUCHIN
Smoke Detectors 4/30/2026 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 5/22/2026 Approved JENNIFER RABUCHIN
Final 5/22/2026 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 5/22/2026 Approved JENNIFER RABUCHIN
HVAC-Final 5/22/2026 Approved JENNIFER RABUCHIN
PLUMBING-Final 5/22/2026 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 5/22/2026 SGSOV Approved JENNIFER RABUCHIN