7725 W JAYSEEL ST 91042
Certificate Information: 7725 W JAYSEEL ST 91042
- Application / Permit
- 25016-20000-30541
- Plan Check / Job No.
- B25VN30049
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: CONVERTING 360 SQ.FT. EXISTING DETACHED GARAGE TO AN ACCESSORY DWELLING UNIT (ADU) PER GCS 66323(a)(1). ALL WORK PER ENG. NFPA 13 D FIRE SPINKLERES REQUIRED THROUGHOUT
- Permit Issued
- Issued on 11/11/2025
- Issuing Office
- Current Status
- CofO Issued on 5/15/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/14/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 10/17/2025 | LUISANGEL VALENZUELA |
| Corrections Issued | 10/18/2025 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 10/29/2025 | LUISANGEL VALENZUELA |
| Plan Check Approved | 11/5/2025 | OMAR GARNICA |
| Issued | 11/11/2025 | APPLICANT |
| CofO in Progress | 4/17/2026 | NICHOLAS TROWBRIDGE |
| Permit Finaled | 5/15/2026 | RUBEN SALAS |
| CofO Issued | 5/15/2026 | RUBEN SALAS |
| Permit Finaled | 5/15/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/27/2025 | JEFF LOREDO |
| Sewer availability | Cleared | 10/27/2025 | JEFF LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 10/30/2025 | JEFF LOREDO |
| Grading Pre-Inspection | Cleared | 11/3/2025 | GERMAN RODRIGUEZ MENDOZA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Danialian,, Derik; Lic. No.: C94256 | 15904 INDEX ST. GRANADA HILLS, CA 91344 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/13/2026 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 1/13/2026 | Approved | NICHOLAS TROWBRIDGE |
| Underground Mechanical | 1/13/2026 | Partial Approval | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 1/23/2026 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Rough | 1/23/2026 | Approved | NICHOLAS TROWBRIDGE |
| Green Building Rough | 1/23/2026 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| HVAC-Rough | 1/23/2026 | Approved | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 1/23/2026 | Approved | NICHOLAS TROWBRIDGE |
| Underground Mechanical | 1/23/2026 | Approved | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 2/2/2026 | Approved | NICHOLAS TROWBRIDGE |
| Green Building Rough | 2/2/2026 | Approved | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 2/2/2026 | Partial Approval | NICHOLAS TROWBRIDGE |
| Shower Pan | 2/2/2026 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Verify Sprinkler Sign Off | 2/2/2026 | Approved | NICHOLAS TROWBRIDGE |
| Insulation | 2/4/2026 | Approved | NICHOLAS TROWBRIDGE |
| Floor/Roof Diaphrgm/Shear Wall | 2/5/2026 | Approved | NICHOLAS TROWBRIDGE |
| Drywall Nailing | 2/6/2026 | Approved | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 2/6/2026 | Approved | NICHOLAS TROWBRIDGE |
| Final | 4/10/2026 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Green Building Final | 4/10/2026 | Approved | NICHOLAS TROWBRIDGE |
| SGSOV-Seismic Gas S/O Valve | 4/10/2026 | SGSOV Approved | NICHOLAS TROWBRIDGE |
| Smoke Detectors | 4/10/2026 | Approved | NICHOLAS TROWBRIDGE |
| Final | 4/16/2026 | OK to Issue CofO | NICHOLAS TROWBRIDGE |