6308 S ALVISO AVE 90043

Certificate Information: 6308 S ALVISO AVE 90043

Application / Permit
25016-20000-30290
Plan Check / Job No.
B25VN29847
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING GARAGE INTO AN ACCESSORY DWELLING UNIT PER GC 66323(a)(1)
Permit Issued
Issued on 1/14/2026
Issuing Office
Valley
Current Status
Issued on 1/14/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/9/2025 APPLICANT
Assigned to Plan Check Engineer 10/16/2025 VAHAN JIVALAGIAN
Assigned to Zoning Architect 10/16/2025 HAYDON CHAN
Corrections Issued 10/19/2025 VAHAN JIVALAGIAN
Quality Review Completed 10/23/2025 OMID HEDAYAT
Building Plans Picked Up 10/24/2025 APPLICANT
Plan Check Approved 1/7/2026 VAHAN JIVALAGIAN
Issued 1/14/2026 APPLICANT

Permit Application Clearance Information

Address approval Cleared 11/14/2025 MICHAEL BROWN
Eng Process Fee Ord 176,300 Cleared 11/14/2025 MICHAEL BROWN
Sewer availability Cleared 11/14/2025 MICHAEL BROWN
Roof/Waste drainage to street Cleared 12/5/2025 ROSE STEIN-WENDT
Zoning Plan Check Cleared 12/17/2025 HAYDON CHAN
Grading Pre-Inspection Cleared 1/7/2026 VAHAN JIVALAGIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Gosen,, James; Lic. No.: C43590 15315 BLEDSOE ST      SYLMAR, CA 91342

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/3/2026 Conditional Approval SCOTT FINNILA
Footing/Foundation/Slab 2/10/2026 Conditional Approval MICHAEL LEWIS
PLUMBING-Rough 2/10/2026 Partial Approval MICHAEL LEWIS
Footing/Foundation/Slab 2/12/2026 Corrections Issued SALVADOR MARTINEZ
Footing/Foundation/Slab 2/17/2026 Not Ready for Inspection LUIS CASTRO
Footing/Foundation/Slab 2/23/2026 Approved SALVADOR MARTINEZ
ELECTRICAL-Rough 3/3/2026 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 3/3/2026 Corrections Issued SALVADOR MARTINEZ
ELECTRICAL-Rough 3/6/2026 Conditional Approval SALVADOR MARTINEZ
HVAC-Rough 3/6/2026 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 3/6/2026 Approved SALVADOR MARTINEZ
Sewer 3/6/2026 Approved SALVADOR MARTINEZ
Underground Mechanical 3/6/2026 Corrections Issued SALVADOR MARTINEZ
BUILDING-Rough-Frame 3/17/2026 Corrections Issued SALVADOR MARTINEZ
ELECTRICAL-Rough 3/17/2026 Approved SALVADOR MARTINEZ
Green Building Rough 3/17/2026 Approved SALVADOR MARTINEZ
HVAC-Rough 3/17/2026 Approved SALVADOR MARTINEZ
Interior/Exterior Lathing 3/17/2026 Partial Approval SALVADOR MARTINEZ
Underground Mechanical 3/17/2026 Conditional Approval SALVADOR MARTINEZ
BUILDING-Rough-Frame 3/23/2026 Corrections Issued SABAS ALONSO
BUILDING-Rough-Frame 4/1/2026 Corrections Issued MICHAEL LEWIS
Insulation 4/1/2026 Approved MICHAEL LEWIS
Shower Pan 4/3/2026 Approved ALEX COLIN
Drywall Nailing 4/8/2026 Approved SALVADOR MARTINEZ
Interior/Exterior Lathing 4/8/2026 Approved SALVADOR MARTINEZ